FIRST DIVISION

[ G.R. Nos. 243029-30, March 18, 2021 ]

TITO S. SARION, PETITIONER, VS. PEOPLE OF THE PHILIPPINES, RESPONDENT.

D E C I S I O N

GAERLAN, J.:

Before this Court is a Petition for Review on certiorari[1] filed by petitioner Tito S. Sarion (petitioner) under Rule 45 of the 1997 Rules of Civil Procedure seeking to annul and set aside the Decision[2] dated September 29, 2017 and Resolution[3] dated November 8, 2018 of the Sandiganbayan in SB-11-CRM-0256 to 0257. The assailed rulings adjudged the petitioner guilty of violating Section 3(e) of Republic Act (R.A.) No. 3019, as amended, otherwise known as the Anti-Graft and Corrupt Practices Act; and Malversation of Public Funds or Property under Article 217 of the Revised Penal Code (RPC).

The Antecedent Facts

The instant controversy arose from a Contract Agreement[4] entered into on December 29, 2003 by herein petitioner, in his capacity as Municipal Mayor for the Municipal Government of Daet, Camarines Norte, and Billy Aceron (Aceron), General Manager of Markbilt Construction (Markbilt), represented by his attorney-in-fact, Architect Romeo B. Itturalde. The agreement had for its purpose the Phase II construction of the Daet Public Market for the amount of P71,499,875.29, which must be completed within a period of 365 calendar days.[5]

On January 5, 2005, the petitioner approved a Notice to Commence Work[6] authorizing Markbilt to commence with the construction project on the 10th day from receipt of the said Notice. Thereafter, construction works proceeded.[7]

Meanwhile, the petitioner's term ended and Elmer E. Panotes (Mayor Panotes) was elected as Municipal Mayor of Daet, Camarines Norte, during the May 2004 national and local elections.[8]

On December 4, 2005 Markbilt, through its engineer Carlito A. Torero, wrote a letter to Mayor Panotes, requesting the verification and proper evaluation of therein attached monthly computation of variation in the prices of materials.[9]

The construction of the Daet Public Market was completed sometime in 2006.[10]

On November 13, 2006, the Office of Mayor Panotes received a letter from Markbilt, requesting the processing and payment of contract price escalation in the amount of P5,222,903.75, in relation to the Daet Public Market (Phase II) project. Mayor Panotes, refused to act on the demand.[11]

During the local elections held in 2007, the petitioner was re-elected as Mayor of the Municipality of Daet.[12]

On January 21, 2008, in a letter addressed to the petitioner, Markbilt reiterated its request for payment of the contract price escalation. A similar demand was made by Markbilt in a letter dated February 7, 2008, this time with the information that it will impose 15% interest per annum on their claim.[13]

With this, the petitioner instructed Municipal Administrator Elmer Nagera (Administrator Nagera) to look for sources of fund to satisfy Markbilt's claim. This gave rise to the creation of Supplemental Budget No. 1. After the same was signed by Municipal Budget Officer Amelia P. Laborte (Budget Officer Laborte) and approved by Administrator Nagera, by authority of the petitioner, Supplemental Budget No. 1 was submitted to the Sangguniang Bayan.[14]

On March 6, 2008, the Sangguniang Bayan passed Resolution No. 063[15] unanimously approving Supplemental Budget No. 1-2008 and appropriating the amount of P11,222,088.00 of the municipality's internal revenue allotment; of such amount, designated under the Special Account, P4,400,000.00 was allotted for the Construction of Market.[16] Resolution No. 063 was later approved by the petitioner.[17]

In another letter dated April 14, 2008, Markbilt reiterated its demand for payment of contract price escalation.[18]

After Budget Officer Laborte certified the existence of available appropriation, Administrator Nagera prepared Obligation Request No. 100-08-03-402 certifying that "the charges to appropriation/allotment are necessary, lawful and under his direct supervision" and that "the supporting documents are valid, proper and legal."[19]

Subsequently, administrator Nagera issued Disbursement Voucher No. 08041239 in the amount of P1,000,000.00, payable to Markbilt, m partial satisfaction of its demand for price escalation.[20]

Concerned with the applicability of R.A. No. 9184, Municipal Accountant Caroline Maisie Robles (Accountant Robles) consulted the Commission on Audit Auditor assigned to the municipality, who in turn, advised him to seek the opinion of the Municipal Legal Officer.[21]

In his opinion, Municipal Legal Officer Edmundo Deveza II (Legal Officer Deveza) found, on the basis of Presidential Decree (P.D.) No. 1594, that there was no reason to refuse the payment of obligation in favor of Markbilt.[22] Thus, on April 21, 2008, Accountant Robles certified the supporting documents complete and the allotment for partial payment of Markbilt. After Municipal Treasurer Arlyn O. Aberia certified that funds were available, the petitioner approved the release of the funds for payment.[23]

On April 24, 2008, Markbilt received payment of P1,000,000.00 made through Landbank Check No. 0272388, and evidenced by Official Receipt No. 1156 dated April 24, 2008.[24]

On June 17, 2008, the Sangguniang Panlalawigan of Camarines Norte approved Resolution No. 229-2008 declaring as operative Supplemental Budget No. 1-2008 of the Municipality of Daet.[25]

On November 27, 2008, Zenaida Baluca, a resident of Daet, Camarines Norte, filed a Complaint[26] against the petitioner before the Deputy Ombudsman for Luzon (Omb-Luzon). The complainant charged the petitioner for violation of Section 3(e) of R.A. No. 3019 relative to the payment of price escalation in the Daet Public Market (Phase II) Project.

After investigation, Graft Investigation and Prosecution officer Judy Anne Doctor-Escalona found merit in the complaint and charged the petitioner with violation of Section 3(e) of R.A. No. 3019, as amended and Malversation, in two separate Informations, the accusatory portions of which read:

SB-11-CRM-0256

That on 24 April 2008 or sometime prior or subsequent thereto, in Daet, a first class municipality in the Province of Camarines Norte, Philippines, and within the jurisdiction of this Honorable Court, the accused, Tito S. Sarion, a public officer, being the Mayor of the Municipality of Daet, committing the crime in the discharge of his official functions, through manifest partiality, evident bad faith, or gross inexcusable negligence, did then and there willfully, unlawfully, and criminally cause undue injury to the government in the gross amount of One Million Pesos, Philippine Currency (PhP1,000,000.00), by then and there approving the disbursement in the absence of certificate of availability of funds, of public funds in said gross amount in favor of Markbilt Construction, the contractor for the construction of Daet Public Market (Phase II), as partial payment for its claim for price escalation which it is not entitled to so receive but which it received nevertheless per its Official Receipt No. 1156 dated 24 April 2008 through the approval of the disbursement voucher by the accused even without the approval from the Government Procurement Policy Board (GPPB) and the determination by the National Economic Development Authority (NEDA) as to the propriety of the claim for price escalation in violation of the GPPB Guidelines for Contract price Escalation to the prejudice of the Municipality of Daet in said amount.

CONTRARY TO LAW.[27]

SB-11-CRM-0257

That on 24 April 2008, or sometime prior or subsequent thereto, in Daet, a first class municipality in the Province of Camarines Norte, Philippines, and within the jurisdiction of this Honorable Court, the accused, Tito S. Sarion, a public officer, being the Mayor of the Municipality of Daet, while in the performance of his official functions, committing the offense in relation to his office, and taking advantage of his official position, and in grave abuse thereof, having control of public funds in the gross amount of One Million Pesos, Philippine Currency (PhP1,000,000.00), which was placed under his administration by reason of the duties of his office, and is accountable for said amount of public funds pursuant to Section 340 of the Local Government Code, did then and there willfully, unlawfully and feloniously consent, or through abandonment or negligence, permit Markbilt Construction, the contractor for the construction of Daet Public Market (Phase II), to take such amount of public funds which it is not entitled to receive but which it received nevertheless per its Official Receipt No. 1156 dated 24 April 2008, by then and there allowing the disbursement through his approval of the disbursement voucher even in the absence of certificate of availability of funds in said gross amount in favor of Markbilt Construction as partial payment for its claim for the price escalation even without the approval from the Government Procurement Policy Board (GPPB) and the determination by the National Economic Development Authority (NEDA) as to the propriety of the claim for price escalation in violation of the GPPB Guidelines for Contract price Escalation.

CONTRARY TO LAW.[28]

The petitioner was conditionally arraigned on September 2, 2011, and assisted by counsel, entered a plea of "not guilty."[29]

After trial, the Third Division of the Sandiganbayan rendered the herein assailed Decision[30] on September 29, 2017, the dispositive portion of which reads:

WHEREFORE, this Court finds accused TITO SARION:

1.
Guilty beyond reasonable doubt of Violation of Section 3(e) of Republic Act No. 3019, and he is accordingly sentenced to:
     

a.
Suffer an indeterminate penalty of imprisonment of Six (6) years and One (1) month, as minimum, to Eight (8) years, as maximum, and,
     

b.
Suffer the penalty of perpetual special disqualification from holding public office; and,
   
2.
Guilty beyond reasonable doubt of Malversation of Public Funds or Property under Article 217 of the Revised Penal Code, and he is accordingly sentenced to:
     

a)
Suffer an indeterminate penalty of imprisonment of Two (2) years, Four (4) months and One (1) day of prision correccional, as minimum, to Six (6) years and One (1) day of prision mayor, as maximum;
     

b)
Pay a fine in the amount of One Million pesos (PhP1,000,000.00); and,
     

c)
Suffer the penalty of perpetual special disqualification from holding public office.

Accused Sarion shall indemnify the Municipality of Daet the amount of One Million Pesos (PhP1,000,000.00) as actual damages, plus interest at the rate of 6% per annum to be reckoned from the date of finality of the Decision until its full satisfaction.

SO ORDERED.[31]

Foremost, the Sandiganbayan found that the prosecution was able to establish the elements of Malversation. Mainly, it held that the petitioner erred in approving Disbursement Voucher No. 08041239 which facilitated the partial payment of contract price escalation in favor of Markbilt although the latter is not entitled to be compensated. The Sandiganbayan ruled that the certificates attesting to the availability of funds and appropriation issued by the municipal officials were irregular and that Appropriation Ordinance No. 1 did not allocate funds for the payment of contract price escalation.[32]

Furthermore, the Sandiganbayan made it clear that under Section 81 of R.A. No. 9184, contract price escalation during the implementation of the contract is expressly prohibited except under extraordinary circumstances as determined by the National Economic Development Authority (NEDA) and upon prior approval of the Government Procurement Policy Board (GPPB).[33] In this case, the Sandiganbayan noted that no such determination and approval were obtained prior to the approval of payment and release of the funds to Markbilt.[34] The petitioner's act of authorizing the release of partial payment to Markbilt without personally confirming compliance with supporting documents is tantamount to gross negligence which subjects him to liability for the crime of Malversation of Public Funds.[35]

With respect to violation of Section 3(e) of RA. No. 3019, the Sandiganbayan equally found the petitioner guilty of the offense. It held that the same act of approving the release without complying with the provisions of RA. No. 9184, constitute gross inexcusable negligence; whereas the payment of contract price escalation in the amount of P1,000,000.00 is an unwarranted benefit in favor of Markbilt and, correspondingly the amount of undue injury caused to the Municipality of Daet.[36]

The petitioner filed a Motion for Reconsideration, but the same was denied by the Sandiganbayan in its Resolution[37] dated November 8, 2018, viz.:

WHEREFORE, accused Tito S. Sarion's Motion for Reconsideration Re: Decision dated September 29, 2017 is DENIED for lack of merit.

SO ORDERED.[38]

Thus, this petition for review on certiorari whereby the petitioner raises the following arguments in support thereof:

1.
The Sandiganbayan seriously erred in convicting him of Malversation of Public Funds under Article 217 of the Revised Penal Code when not all the elements thereof were proved by the plaintiff, through prosecution, beyond reasonable doubt.


2.
The Sandiganbayan seriously erred in convicting him of Violation of Section 3(e) of Republic Act No. 3019 when not all the elements thereof were proved by the plaintiff, through the prosecution, beyond reasonable doubt.[39]

Ruling of the Court

The petition is not meritorious.

Petitioner, in this appeal, alleges that the Sandiganbayan erred in convicting him of the crime of Malversation under Article 217 of the RPC, and for violation of Section 3(e) of R.A. No. 3019, submitting that not all the elements thereof have been proven by the prosecution beyond reasonable doubt.

On this score, it is imperative to point out at the outset that this appeal is in the nature of a petition for review on certiorari. In the exercise of the Court's appellate jurisdiction over the decision of the Sandiganbayan, it is settled that this mode of review is limited only to questions of law. The factual findings of the Sandiganbayan are, as a general rule, conclusive upon the Court.[40]

The difference between a question of law and a question of fact has been settled. A question of law exists when there is doubt or controversy as to what the law is on a certain set of facts. In contrast, what is involved is a question of fact when the resolution of the same demands the calibration of evidence, the determination of the credibility of witnesses, the existence and the relevance of the attendant circumstances, and the probability of specific situations.[41] Thus, the issues of "whether the prosecution's evidence proved the guilt of the accused beyond reasonable doubt, whether the presumption of innocence was properly accorded the accused, x x x or whether the defense of good faith was correctly appreciated," submitted herein by the petitioner, are all, albeit in varying degrees, questions of fact.[42]

The petitioner, in arguing the absence of elements of the crimes with which he is charged, in effect seeks a re-evaluation of the Sandiganbayan's appreciation of the sufficiency of evidence presented. The general rule is that these factual findings of the Sandiganbayan are conclusive upon the Court, save for certain exceptions, viz.:

(1) the conclusion is a finding grounded entirely on speculations, surmise[s], and conjectures; (2) the inference made is manifestly mistaken; (3) there is grave abuse of discretion; (4) the judgment is based on misapprehension of facts; and [(5)] the findings of fact of the Sandiganbayan are premised on the absence of evidence and are contradicted by evidence on record.[43]

None of these exceptions obtains in this case. Thus, there is no reason to deviate from the factual findings of the Sandiganbayan.

With respect to the crime of malversation, the petitioner posits that he cannot be convicted of the offense as the elements of official custody of funds and accountability therefor, and the act of misappropriation are missing.[44]

He claims that contrary to the findings of the Sandiganbayan, there were prior certifications for availability of funds before he signed the disbursement voucher. These certifications were not irregular as Supplemental Budget No. 1, which was approved by the Sangguniang Bayan, provided for appropriation in the amount of P1,000,000.00 in favor of Markbilt.[45] Petitioner asserts that he has no custody or control over such amount paid to Markbilt.[46]

Moreover, petitioner argues that the responsibility of ensuring that the requirements of Section 61 of R.A. No. 9184 are met does not belong to him but to Markbilt. At any rate, even claiming such responsibility, petitioner suggests that failure to comply with the said requirements should not be penalized as the law does not provide any penal sanctions.[47]

Finally, petitioner submits that he had the right to rely upon the legal opinion of the Municipal Legal Officer, which is presumed regular; and that he acted in good faith, a valid defense in malversation as it indicates the absence of criminal intent.[48]

The elements common to all acts of malversation under Article 217 of the Revised Penal Code, as amended, are the following: (a) that the offender is a public officer; (b) that he had custody or control of funds or property by reason of the duties of his office; (c) that those funds or property were public funds or property for which he was accountable; and (d) that he appropriated, took, misappropriated or consented, or through abandonment or negligence, permitted another person to take them.[49]

Applied in this case, it is undisputed that the petitioner is a public officer, being then elected Municipal Mayor of Daet and that the funds involved are public in character, as they belong to the Municipality of Daet.

Contrary to his allegation, petitioner is by reason of his office, an accountable officer. Section 340 of the Local Government Code (LGC) provides:

Section 340. Persons Accountable for Local Government Funds. - Any officer of the local government unit whose duty permits or requires the possession or custody of local government funds shall be accountable and responsible for the safekeeping thereof in conformity with the provisions of this title. Other local officials, though not accountable by the nature of their duties, may likewise be similarly held accountable and responsible for local government funds through their participation in the use or application thereof.

Based on the foregoing provision, local government officials are accountable public officers either because of the nature of their functions, or on account of their participation in the use or application of public funds. In this case, the funds paid to Markbilt form part of the internal revenue allotment of the Municipality of Daet and are by virtue thereof, "under the collective custody of the municipal officials who had to act together to disburse the funds for their intended municipal use."[50] Consequently, they are public funds for which the petitioner as Municipal Mayor is accountable.[51]

More unequivocal, Presidential Decree (P.D.) No. 1445 or the Government Auditing Code of the Philippines states that municipal mayors are immediately and primarily responsible for all government funds and property pertaining to their municipality.[52]

As a required standard procedure,[53] and evidently from petitioner's own narration, any disbursement or release of funds requires his approval as Mayor. In this case, payment in favor of Markbilt was released only after petitioner's signature in the disbursement voucher and the corresponding Landbank check. This signifies that petitioner, in his capacity as Municipal Mayor, had control and responsibility over the subject funds[54] and thus satisfies the second and third elements of the offense.

Finally, on the last element, the Court agrees with the Sandiganbayan that the petitioner, through gross inexcusable negligence, permitted Markbilt to receive partial payment of price escalation despite not being entitled thereto. A disbursement voucher "shows on what account or by what authority a particular payment has been made, or that services have been performed which entitle the party to whom it is issued to payment."[55] Thus, when petitioner signed the disbursement voucher in favor of Markbilt, in effect, he certified to the correctness of the entries therein; and warranted that the expenses incurred were necessary and lawful, the supporting documents were complete, and the availability of cash therefor.[56] By approving the disbursement voucher and signing the Landbank check payable to Markbilt, despite the absence of funding and failure to comply with the requirements of Section 61, R.A. No. 9184, he permitted Markbilt to receive public funds to which it is not entitled. Otherwise, the petitioner's approval and signature in respect facilitated the illegal release of funds, constitutive of the act of malversation.

Malversation may be committed intentionally (dolo) or by means of negligence (culpa). The crime is committed by means of dolo when the act is accompanied by criminal intent as when the offender misappropriated or converted public funds of property to one's personal use.[57] Malversation may also be committed by means of culpa or by such negligence or indifference to duty or to consequences as, in law is equivalent to criminal intent;[58] as when the offender knowingly allowed another or others to make use of or misappropriate public funds or property.[59]

It is a basic principle that no contract involving the expenditure of public funds shall be entered into unless there is an appropriation therefor which is sufficient to cover the proposed expenditure.[60] Correspondingly, no revenue funds shall be paid out of the public treasury except in pursuance of an appropriation law or specific statutory authority.[61] The act of petitioner in approving Disbursement voucher No. 08041239 and signing Landbank check No. 0272388 in violation of the said elementary principles is a flagrant and palpable breach of duty tantamount to gross negligence.[62]

In this case, as correctly ruled by the Sandiganbayan, the payment of price escalation is not supported by an appropriation. Pursuant to the Contract Agreement[63] dated December 29, 2003, relative to the Phase II construction of the Daet Public Market, petitioner and Markbilt agreed for the construction to completed within a period of 365 calendar days for the amount of P71,499,875.29. The statement of such amount constitutes the specific appropriation required by law for a specific expenditure, that is, the entirety of the Daet Public Market (Phase II) construction project.

The basis of Markbilt's claim for price escalation is based on the same contract, particularly, clause no. 4, which states:

4. The Implementing Rules and Guidelines regarding Adjustment of contract prices adopted and approved by the Government will be applied in this contract.[64]

The provision authorizes the claim for price escalation, without any reference as to the source of funds for its satisfaction. To the Court, it is a vague recognition of Markbilt's right to collect over and beyond the contract price. A cursory reading thereof shows that it does not provide additional rights in favor of Markbilt. It merely mentions what is evident and otherwise impliedly included in the contract, i.e., that pertinent laws and rules apply in the event of the need to adjust contract price arises. As the Court sees it, the invocation of this clause in the Contract Agreement is a vain attempt to circumvent the requirement that there be a specific appropriation for any disbursement.

What is crucial is that in the absence of appropriation or designation of source of funds, the aforestated clause cannot be considered as a source of an enforceable right in favor of Markbilt. Section 85 in relation to Section 86 of P.D. No. 1445, requires the existence of a prior sufficient appropriation, as certified by the proper accounting official, before any contract for expenditure of public funds is authorized, viz.:

Section 85. Appropriation before entering into contract.

(1) No contract involving the expenditure of public funds shall be entered into unless there is an appropriation therefor, the unexpended balance of which, free of other obligations, is sufficient to cover the proposed expenditure.

x x x x

Section 86. Certificate showing appropriation to meet contract. Except in the case of a contract for personal service, for supplies for current consumption or to be carried in stock not exceeding the estimated consumption for three months, or banking transactions of government­ owned or controlled banks, no contract involving the expenditure of public funds by any government agency shall be entered into or authorized unless the proper accounting official of the agency concerned shall have certified to the officer entering into the obligation that funds have been duly appropriated for that the amount necessary to cover the proposed contract for the current fiscal year is available for expenditure on account thereof, subject to verification by the auditor concerned. The certificate, signed by the proper accounting official and the auditor who verified it, shall be attached to and become an integral part of the proposed contract, and the sum so certified shall not thereafter be available for expenditure for any other purpose until the obligation of the government agency concerned under the contract is fully extinguished. (Underscoring supplied)

The only appropriation in this case is the original contract price of P71,499,875.29. Consequently, no payment can be made beyond such amount. In the same way, as there is no funding to support the price escalation clause in the said Contract Agreement, no public funds can be disbursed in payment thereof. The clause is void and of no effect.[65] It cannot be enforced and the public officer who entered into the contract without such appropriation and certification shall be liable for any resulting damage to the government.[66]

For the sake of argument, even assuming the validity of the contract clause authorizing price escalation, the Court nonetheless finds that the additional budget certified and approved does not provide for payment of price escalation in favor of Markbilt.

Petitioner argues that Supplemental Budget No. 1 signed by the Municipal Budget Officer Laborte and approved by Municipal Administrator Nagera, on his authority, and of the Sangguniang Bayan, provided for appropriation m the amount of P1M in favor of Markbilt Construction.[67]

Appropriation Ordinance No. 1 passed by the Sangguniang Bayan on March 6, 2008, which approved Supplemental Budget No. 1, provides:

AN ORDINANCE APPROVING THE SUPPLEMENTAL BUDGET NO. 01 FOR CY 2008 FOR THE MUNICIPALITY OF DAET APPROPRIATING x x x FOR SPECIAL ACCOUNT (MARKET) - CONSTRUCTION OF PUBLIC MARKET AMOUNTING TO FOUR MILLION FOUR HUNDRED THOUSAND PESOS (P4,400,000.00) x x x

SECTION 1. The amount of P11,222,088.00 is hereby appropriated as follows:

x x x x

Special Account (market)
Construction of Market
4,400,000.00
 
     
TOTAL SUPPLEMENTAL APPROPRIATIONS
P11,222,088.00
 

SECTION 2. The Municipal Treasurer, Municipal Accountant and the Municipal Budget Officer are hereby authorized to effect payment and corresponding adjustments be made in the book of accounts.

SECTION 3. This appropriation ordinance shall take effect upon approval.[68]

Contrary to the submission of the petitioner, a cursory reading of the appropriation ordinance clearly shows that it does not cover the payment for price escalation. Understood by its plain and ordinary meaning,[69] the supplemental budget refers to the further construction of the Daet public market. It pertains to future works to be done, and not of past work performed. Had it been the intention of the Sangguniang Bayan to pay for the price escalation on completed works, it could have employed a more direct language than that employed, such as "works done." In the absence of evidence showing legislative intent of the Sangguniang Bayan to the contrary, the Court cannot stretch the meaning of the law. An appropriation may be used only for the specific purpose for which they are appropriated.[70] The Court quotes with approval the Sandiganbayan's elucidation:

Appropriation Ordinance No. 1 contained no appropriation for the payment of the amount of Php1,000,000.00 to Markbilt. Appropriation Ordinance No. 1 shows that the appropriation was for the construction of the public market. There was no appropriation to pay for the contract price escalation, an obligation supposedly incurred in the already completed construction of the Daet Public Market.

Accused Sarion and his witnesses point to the deliberations of the Sangguniang Bayan. But the intent to pay the alleged contract price escalation allegedly manifested during the deliberations are not reflected in Appropriation Ordinance No. 1. Notably, no documentary evidence was offered to prove the alleged deliberations.[71]

In the herein assailed ruling of the Sandiganbayan, it held that despite the issue with respect to funding, the petitioner cannot be held culpable as "the Information alleges the absence of, not the infirmity in, the certificate of availability of funds."[72]

The Court does not agree.

An Information is sufficient when it states the designation of the offense and the acts or omissions which constitute the offense charged. The crime must be described in ordinary and concise language and with such particularity and reasonable certainty that the accused is duly informed of the offense charged and able to adequately prepare for his defense.[73] "In particular, whether an Information validly charges an offense depends on whether the material facts alleged in the complaint or information shall establish the essential elements of the offense charged as defined in the law."[74]

To recapitulate, Section 86 of P.D. No. 1445 requires the existence of a prior specific appropriation, as certified by the proper accounting official, before any contract for expenditure of public funds is authorized. In this sense, therefore, it is the absence of certification as to the availability of or source of funds pertaining specifically to the payment of price escalation, that rendered the clause void and the subsequent approval by the petitioner of the disbursement voucher invalid. It is this irregularity which rendered the payment in favor of Markbilt illegal. In tum, it is the transgression of the same basic principle in disbursement of public funds which translates to gross negligence on the part of the petitioner. With this, the elements of the offense sufficiently alleged and proven in the Information, there is no obstacle in convicting the petitioner of the crime of malversation.

At any rate, granting for the sake of argument that the failure of the Information to specifically employ the word "irregularity" instead of "absence" constitutes a violation of the petitioner's right to Information and as such may not be considered in determining the offenses charged, the petitioner may nonetheless be still be convicted of the crime of malversation and for violation of Section 3(e) of R.A. No. 3019 "through [his] approval of the disbursement voucher x x x even without the approval from the Government Procurement Policy Board (GPPB) and the determination by the National Economic Development Authority (NEDA) as to the propriety of the claim for price escalation in violation of the GPPB Guidelines for Contract price Escalation,"[75] clearly stated and alleged in the two (2) Informations filed against him. As will further be illustrated hereunder, this fact establishes the elements of the subject offenses as defined by law.

As correctly ruled by the Sandiganbayan, in addition to the requirement of appropriation and certification of availability of funds, price escalation during the implementation of a contract must comply with the requirements of R.A. No. 9184 or the Government Procurement Reform Act.

It is a basic rule that the laws in force at the time the contract was made governs its interpretation and application.[76] In this case, the Contract Agreement between the parties was executed on December 29, 2003. At that time, the law in effect is R.A. No. 9184. By express repeal, the Act, which took effect on January 26, 2003, superseded P.D. No. 1594.[77]

Section 61[78] of R.A. No. 9184 explicitly provides that any given scope of work in the contract as awarded shall be for the fixed price specified therein. Any increase in the contract price is subject to prior determination by the NEDA of the existence of an extraordinary circumstance and approval of the GPPB. It is only after which that contract price escalation may be authorized and paid.[79]

The provision is clarified by the rules implementing R.A. No. 9184[80] which was then in effect at the time of the contract, viz.:

Section 61. Contract Prices

x x x x

61.2. Any request for price escalation under extraordinary circumstances shall be submitted by the concerned entity to the National Economic and Development Authority (NEDA) with the endorsement of the procuring entity. The burden of proving the occurrence of extraordinary circumstances that will allow for price escalation shall rest with the entity requesting for such escalation. NEDA shall only respond to such request after receiving the proof and the necessary documentation.

61.3. For purposes of this Section, "extraordinary circumstances" shall refer to events that may be determined by the NEDA in accordance with the Civil Code of the Philippines, and upon the recommendation of the procuring entity concerned.

Evidently, price escalation in a contract for public works is not immediately executory by mere specification in contract. There is a procedure to be followed. A recommendation must first be made by the procuring entity of the existence of an extraordinary circumstance. Then, the NEDA would make a determination confirming the justification offered by the procuring entity. After finding that an extraordinary circumstance exists thus justifying the payment of price escalation, the request would have to be forwarded to the GPPB for approval.[81] It is only after the GPPB signifies its approval of the price escalation claim that the payment can be processed and released by the government entity concerned to the contractor.

In this case, it is not contested that the petitioner failed to observe the foregoing procedure prior to his approval of the disbursement voucher and signing of the Landbank check in favor of Markbilt. This is supported by a Certification[82] dated July 25, 2012 issued by the NEDA to the effect that it had not received any request from the Municipality of Daet for exemption and/or approval for the payment of escalation price.

In justifying the failure to comply with the requirements of R.A. No. 9184, the petitioner posits that it had the right to rely upon the legal opinion of Legal Officer Deveza that there was no reason to refuse the payment of obligation to Markbilt. He argues that the same is complete, adequately supported by sufficient legal principles, and has in its favor the presumption of regularity which the prosecution herein failed to rebut.[83]

The petitioner also raised the defense of good faith to negate criminal intent in the charge for malversation. Succinctly, he claims that the doctrine in Arias v. Sandiganbayan[84] is applicable to him. Petitioner claims that in approving the payment of price escalation in favor of Markbilt, he merely relied in good faith on the opinion of Legal Officer Deveza, the certifications and approval of Budget Officer Laborte and other local officials, and the presumed validity of Appropriation No. 1.[85]

The ruling in Arias does not apply; it cannot exculpate petitioner from liability. In Arias, the Court held that "[a]ll heads of offices have to rely to a reasonable extent on their subordinates and on the good faith of those who prepare bids, purchase supplies, or enter into negotiations."[86] In subsequent cases, it was made clear nonetheless that "the Arias doctrine is not an absolute rule. It is not a magic cloak that can be used as a cover by a public officer to conceal himself in the shadows of his subordinates and necessarily escape liability."[87] When there are circumstances that should have alerted heads of offices to exercise a higher degree of circumspection in the performance of their duties, they cannot invoke the doctrine to escape liability. In this scenario, heads of offices are expected to exercise more diligence and go beyond what their subordinates have prepared.[88]

In the same vein, the presumption of regularity "obtains only when there is no deviation from the regular performance of duty. Where the official act in question is irregular on its face, no presumption of regularity can arise."[89]

In this case, the Court finds the existence of such circumstances which could have alerted the petitioner to inquire further prior to his approval of the disbursement voucher, beyond the certifications and documents issued by municipal officials.

To recall, the Contract Agreement for the construction of the Daet Public Market (Phase II) was entered into on December 29, 2003, during the petitioner's term as Municipal Mayor. Actual construction commenced in January 2005.[90] Months thereafter or in December 2005, allegedly on account of spiraling costs of materials during the construction period, Markbilt filed a claim for the adjustment of contract price pursuant to the price escalation clause of the Contract Agreement.[91] This was followed by successive requests for price escalation,[92] viz.:

Billing Date
Amount
Period Covered
April 25, 2004
P 76,282.99
February 19, 2004-April 16, 2004
July 15, 2004
2,041,842.15
April 17, 2004-July 13, 2004
September 26, 2004
1,647,087.36
July 14, 2004-September 23, 2004
February 28, 2005
1,457,700.24
September 24, 2004-February 23, 2005
Total
P 5,222,903.74
 

During the intervening period or in May 2004, Mayor Panotes was elected as Municipal Mayor of Daet It was sometime in June 2005, during his term, that the Phase II construction project was completed. Thereafter, Markbilt continued to file several letter-requests reiterating its claim for price escalation. However, then Mayor Panotes refused to act upon the claims until the end of his term in June 2007. It was when the petitioner was re-elected that Markbilt's claim was processed and eventually paid in May 2008.[93]

Considering that two years had passed since the project's completion and more than three years since the first demand for payment of price escalation was made by Markbilt, the petitioner could have inquired into the circumstances attending the demand and the construction project and why the same was unacted upon by his predecessor. Instead of immediately instructing Administrator Nagera to look for sources of funds, he should have sought the opinion of the Municipal Engineer. Petitioner should have at the very least referred the documents relative to construction project to the appropriate municipal officials for study in order to verify the basis of Markbilt's claim. This is particularly relevant as majority of the project was undertaken and ultimately completed prior to his term. As well, the amount appropriated for the Daet Public Market (Phase II) construction project has already been fully released. Markbilt's demand is over and beyond the contract price and dependent upon the cost of materials almost three years passed. Simply, the propriety of Markbilt's additional claim depends upon the prevailing market prices at the time they were purchased vis-à-vis the costs when the contract was entered into. In this regard, prudence dictates that further verification be conducted as to the veracity of the amount claimed by Markbilt. The amount involved is by no means trivial; it involves millions of pesos of public funds. Petitioner, as head of office, should have taken this precaution in order to safeguard the government funds for which he is responsible[94] and to protect the interests of the municipality.

In this case, after receiving Markbilt's demand, petitioner immediately referred the same to Administrator Nageta and instructed him to look for sources of funds in order to satisfy the same, without taking steps first in order to verify the propriety of Markbilt's additional claim for payment. It is this act which set the process in motion. Ultimately, it was the petitioner's signature on the disbursement voucher and Landbank check that allowed Markbilt to encash the P1,000,000.00 partial payment for contract price escalation, despite not being entitled thereto. This satisfied the last element of the offense and rendered the crime of malversation complete.

The petitioner was also charged with violation of Section 3(e) of R.A. No. 3019,[95] the elements of which are the following:

a) The accused must be a public officer discharging administrative, judicial or official functions;

b) He must have acted with manifest partiality, evident bad faith or inexcusable negligence; and

c) That his action caused any undue injury to any party, including the government, or giving any private party unwarranted benefits, advantage or preference in the discharge of his functions.[96]

As defined and applied in this case, the offense has common elements with the crime of malversation, in particular, the first and second elements. Having previously elucidated on the same, the Court need not discuss the same in detail.

In approving the release of payment in favor of Markbilt, it is no contest that the petitioner acted in the performance of his administrative and official functions.

Moving on to the second element, for a successful prosecution under Section 3(e) of R.A. No. 3019, it is not enough that undue injury was caused, the act must be performed through manifest partiality, evident bad faith, or gross inexcusable negligence.[97] Pertinent to the issue at hand, "gross inexcusable negligence" has been defined as –

[t]he want of even slight care, acting or omitting to act in a situation where there is a duty to act, not inadvertently but willfully and intentionally with a conscious indifference to consequences in so far as other persons may be affected. It is the omission of that care which even inattentive and thoughtless men never fail to take on their own property.[98]

The Court affirms that the petitioner is guilty of gross inexcusable negligence amounting to bad faith. From the stated definition, there is gross inexcusable negligence when a public officer commits a breach of duty in a blatant and extremely careless manner; or when the violation of law is serious, flagrant, palpable, or there is willful indifference in complying with the same.

As previously discussed, the petitioner was remiss in his duty when he failed to exercise diligence in ensuring compliance with basic requirements demanded by the law, rules, and regulations in the disbursement of public funds. First, as the signatory in the Contract Agreement with Markbilt, he is presumed to know the contents thereof. On its face, the instrument only provides for a single appropriation for the construction project; there is no separate funding to support the contract price escalation clause therein. In the statement of the said clause, the parties covenant to comply with relevant rules and regulations with respect to the same. Albeit unnecessary, they explicitly incorporated the relevant guidelines with respect to adjustment of contract prices. Thus, upon receipt of Markbilt's demand for price escalation, prudence dictates for the petitioner to first verify the propriety of the said claim and whether the said claim satisfies the requirements of applicable laws. It is only then that the possibility of satisfying the claim can even be entertained. It is highly irregular and unusual to rely merely on the representation of the contractor as to the amount due, without validating whether the amount so claimed is accurate and correct. Likewise, it must be noted that petitioner was already confronted with Markbilt's demands for price escalation as early as January 21, 2008. Even so, there was no evidence on record of any effort on the part of the petitioner to direct municipal officials to inquire on the basis of Markbilt's claims vis-à-vis the Contract Agreement which is cited as basis therefor, when he had every opportunity to do so prior to release of Legal Officer Deveza's opinion and the preparation of the Supplemental Budget. This step could have easily alerted the petitioner or the municipal officials of the requirements of price escalation under the law, particularly that provided for under Sec. 61 of R.A. No. 9184.

Had the petitioner undertaken these steps, he would have realized, for reasons previously stated in this decision, that Markbilt's claim should be denied. The petitioner's failure to observe sufficient diligence under these circumstances, which led to violation of the law and the rules relating to disbursement of public funds amounts to gross inexcusable negligence.

Finally, the Court likewise finds that the prosecution was able to prove the element of undue injury. Jurisprudence defined "undue injury" as actual damage established by evidence as caused by the questioned conduct by the offender.[99]

The petitioner's approval of the disbursement voucher and signature in the Landbank check in favor of Markbilt facilitated the unauthorized release of P1,000,000.00 of public funds which belong to the Municipality of Daet. As it is established that Markbilt is not entitled to such payment, the Sandiganbayan was correct in ruling that the petitioner caused undue injury in this amount, which then petitioner must return.

With respect to the penalty, the Court finds the penalties imposed by the Sandiganbayan to be in order and should not be disturbed.

Article 217 of the RPC, as amended by R.A. No. 10951,[100] provides that a person guilty of malversation shall suffer the penalty of prision mayor in its minimum and medium periods, if the amount involved is more than P40,000.00 but does not exceed P1,200,000.00.[101] Applying the Indeterminate Sentence Law (ISL),[102] the imposable minimum penalty shall be anywhere within prision correccional in its medium and maximum periods or 2 years, 4 months and 1 day to 6 years. In view of the mitigating circumstance of voluntary surrender, the maximum penalty, on the other hand, shall be within the minimum period of prision mayor in its minimum and medium periods or 6 years and 1 day to 7 years and 4 months.[103] The indeterminate penalty of imprisonment of two (2) years, four (4) months and one (1) day of prision correccional, as minimum, to six (6) years and one (1) day of prision mayor, as maximum; imposed by the Sandiganbayan which is within the stated range, is hereby affirmed. In addition, as adjudged, likewise by virtue of Article 217 of the RPC, petitioner must also be meted with the accessory penalty of perpetual disqualification from holding public office and ordered to pay a fine equal to the amount of funds malversed, herein equivalent to P1,000,000.00 plus interest thereon at the rate of six percent (6%) per annum, reckoned from the finality of this Decision until fully paid.[104]

Whereas, under Section 9(a)[105] of R.A. No. 3019, a person found guilty of violating Section 3(e) of the same law is punishable with imprisonment for not less than six (6) years and one (1) month nor more than fifteen (15) years, and perpetual disqualification from public office. Applying the ISL, the penalty shall not be less than the minimum term nor exceed the maximum term fixed by the law.[106] Thus, the penalty imposed by the Sandiganbayan which is indeterminate penalty of imprisonment of six (6) years and one (1) month, as minimum, to eight (8) years, as maximum, is in accord with law.

WHEREFORE, in view of the foregoing, the instant petition for review on certiorari is hereby DENIED. The Decision dated September 29, 2017 and the Resolution dated November 8, 2018 of the Sandiganbayan in SB-11-CRM-0256 to 0257, finding petitioner Tito S. Sarion GUILTY beyond reasonable doubt of the crime of Malversation of Public Funds under Article 217 of the Revised Penal Code and of violating Section 3(e) of Republic Act No. 3019, are hereby AFFIRMED.

SO ORDERED.

Carandang and Zalameda, JJ., concur.
Caguioa, J.
, please see dissenting opinion.
Peralta, C.J., join in the dissent of J. Caguioa.


[1] Rollo, pp. 11-90.

[2] Id. at 95-119b; penned by Associate Justice Sarah Jane T. Fernandez, with Presiding Justice Amparo M. Cabotaje-Tang and Associate Justice Bernelito R. Fernandez.

[3] Id. at 121-130.

[4] Id. at 169-172.

[5] Id. at 107b-108.

[6] Id. at 173.

[7] Id. at 108.

[8] Id.

[9] Id.

[10] Id.

[11] Id. at 108-108b.

[12] Id.

[13] Id. at 108b.

[14] Id.

[15] Id. at 174-176.

[16] Id. at 108b, 176.

[17] Id.

[18] Id.

[19] Id. at 109.

[20] Id.

[21] Id.

[22] Id. at 109-109b.

[23] Id. at 109b.

[24] Id.

[25] Id.

[26] Id. at 181-191.

[27] Id. at 135-136.

[28] Id. at 132-133.

[29] Id. at 96.

[30] Id. at 95-119b.

[31] Id. at 118b-119.

[32] Id. at 111-112.

[33] Id. at 112b-113.

[34] Id. at 113b-114.

[35] Id. at 114-115b.

[36] Id. at 115b-118.

[37] Id. at 121-130.

[38] Id. at 119.

[39] Id. at 39.

[40] Zoleta v. Sandiganbayan (Fourth Div.), et al., 765 Phil. 39, 52 (2015).

[41] Id.

[42] Jaca v. People, et al., 702 Phil. 210, 238 (2013).

[43] Pareño v. Sandiganbayan, 326 Phil. 255, 279 (1996).

[44] Rollo, p. 41.

[45] Id. at 43, 47-48.

[46] Id. at 54-55.

[47] Id. at 52-54.

[48] Id. at 60-62, 64.

[49] Zoleta v. Sandiganbayan (Fourth Div.), et al., supra note 40 at 53.

[50] Manuel, et al. v. Sandiganbayan, et al., 681 Phil. 273, 292 (2012).

[51] Id.

[52] See Section 444 (a), Local Government Code in relation to Section 102 (1), P.D. No. 1445:

Sec. 444. The Chief Executive: Powers, Duties, Functions and Compensation. (a) The municipal mayor, as chief executive of the municipal government, shall exercise such powers and performs such duties and functions as provided by this Code and other laws. x x x

Section 102. Primary and secondary responsibility. - (1) The head of any agency of the government is immediately and primarily responsible for all government funds and property pertaining to his agency.

[53] Section 39 of the Manual on the New Government Accounting System for Local Government Units

Sec. 39. Approval of Disbursements. - Approval of disbursements by the Local Chief Executive (LCE) himself shall be required whenever local funds are disbursed, except for regularly recurring administrative expenses such as: payrolls for regular or permanent employees, expenses for light, water, telephone and telegraph services, remittances to government creditor agencies such as GSIS, BIR, PHILHEALTH, LBP, DBP, NPO, PS of the DBM and others, where the authority to approve may be delegated. Disbursement vouchers for expenditures appropriated for the operation of the Sanggunian shall be approved by the provincial Vice Governor, the city Vice-Mayor or the municipal Vice-Mayor, as the case may be.

[54] Cf. Zoleta v. Sandiganbayan (Fourth Div.), et al., supra note 40 at 54.

[55] Id.

[56] Id.

[57] Felicilda v. Justice Grospe, 286 Phil. 384, 389 (1992).

[58] Tabuena v. Sandiganbayan, 335 Phil. 795, 822 (1997), citing United States v. Catolico, 18 Phil. 504, 506-507 (1911) and United States v. Elviña, 24 Phil. 230, 231-232 (1913).

[59] Felicilda v. Justice Grospe, supra, citing People v. Miranda, 112 Phil. 197, 200 (1961).

[60] PRESIDENTIAL DECREE No. 1445, Section 85, Government Auditing Code of the Philippines.

[61] CONSTITUTION, Article VI, Section 29(1); REPUBLIC ACT NO. 7160, Section 305(a), Local Government Code; PRESIDENTIAL DECREE No. 1445, Section 84, Government Auditing Code of the Philippines.

[62] Diego v. Sandiganbayan, 394 Phil. 88, 101 (2000).

[63] Rollo, pp. 169-172.

[64] Id. at 170.

[65] Section 87. Void contract and liability of officer. Any contract entered into contrary to the requirements of the two immediately preceding sections shall be void, and the officer or officers entering into the contract shall be liable to the government or other contracting party for any consequent damage to the same extent as if the transaction had been wholly between private parties.

[66] Id.

[67] Rollo, pp. 47-48.

[68] Id. at 174-176.

[69] In Funa v. Chairman Villar, 686 Phil. 571, 591-592 (2012) the Court held that "if a statute or constitutional provision is clear, plain and free from ambiguity, it must be given its literal meaning and applied without attempted interpretation. This is known as the plain meaning rule enunciated by the maxim verba legis non est recedendum, or from the words of a statute there should be no departure."

[70] Local Government Code, Sections 306 (b) and 336.

[71] Rollo, p. 112.

[72] Id.

[73] REVISED RULES OF CRIMINAL PROCEDURE, Rule 110, Sections 6 and 9. Jaca v. People, et al., supra note 42 at 238-239.

[74] Jaca v. People, et al., id.

[75] Rollo, pp. 135-136.

[76] Banco Filipino Savings and Mortgage Bank v. Ybañez, 486 Phil. 1148, 1156 (2004).

[77] PRESIDENTIAL DECREE NO. 1594, Section 76.

[78] SEC. 61. Contract Prices. - For the given scope of work in the contract as awarded, all bid prices shall be considered as fixed prices, and therefore not subject to price escalation during contract implementation, except under extraordinary circumstances and upon prior approval of the GPPB.

For purposes of this Section, "extraordinary circumstances" shall refer to events that may be determined by the National Economic and Development Authority in accordance with the Civil Code of the Philippines, and upon the recommendation of the procuring entity concerned.

[79] Id., Guidelines for Contract Price Escalation, GPPB Resolution No. 07-2004, October 19, 2004.

[80] Approved through Memorandum Order No. 119 dated September 18, 2003 and took effect fifteen (15) days after its publication or on October 8, 2003.

[81] 5.6, Guidelines for Contract Price Escalation, GPPB Resolution No. 07-2004, October 19, 2004.

5.6 Recommendation/Approval. NEDA shall, upon completion of its review pursuant to Section 5.2 hereof, submit its recommendations to the GPPB for appropriate action. The GPPB shall then approve/act upon the request for price escalation during one of its meetings, to be attended by the Head of the Procuring Entity concerned or his duly authorized representative/s.

[82] Rollo, p. 260.

[83] Id. at 64.

[84] 259 Phil. 794 (1989).

[85] Rollo, p. 61.

[86] Arias v. Sandiganbayan, supra at 796.

[87] Rivera v. People, 749 Phil. 124, 151-152 (2014).

[88] Id.

[89] People v. Alejandro, 671 Phil. 33, 54 (2011).

[90] Rollo, pp. 108, 173.

[91] Id. at 244.

[92] Id. at 255.

[93] Id. at 244-245.

[94] PRESIDENTIAL DECREE NO. 1445, Section 102(b).

[95] Sec. 3. Corrupt practices of public officers. In addition to acts or omissions of public officers already penalized by existing law, the following shall constitute corrupt practices of any public officer and are hereby declared to be unlawful:

(e) Causing any undue injury to any party, including the Government, or giving any private party any unwarranted benefits, advantage or preference in the discharge of his official administrative or judicial functions through manifest partiality, evident bad faith or gross inexcusable negligence. This provision shall apply to officers and employees of offices or government corporations charged with the grant of licenses or permits or other concessions.

[96] Consigna v. People, et al., 731 Phil. 108, 123-124 (2014).

[97] Rivera v. People, 749 Phil. 124, 141-142 (2014).

[98] Coloma, Jr. v. Sandiganbayan, et al., 744 Phil. 214, 229 (2014), citing Fonacier v. Sandiganbayan, 308 Phil. 660, 693-694 (1994).

[99] Bacasmas v. Sanidganbayan, et al., 713 Phil. 639, 663 (2013).

[100] AN ACT ADJUSTING THE AMOUNT OR THE VALUE OF PROPERTY AND DAMAGE ON WHICH A PENALTY IS BASED, AND THE FINES IMPOSED UNDER THE REVISED PENAL CODE, AMENDING FOR THE PURPOSE ACT NO. 3815, OTHERWISE KNOWN AS "THE REVISED PENAL CODE," AS AMENDED. Approved on August 29, 2017.

Section 100. Retroactive Effect. - This act shall have retroactive effect to the extent that it is favorable to the accused or person serving the sentence by final judgment.

[101] REPUBLIC ACT NO. 10951, Section 40(2).

[102] REPUBLIC ACT NO. 4103, Section 1 reads:

Section 1. Hereafter, in imposing a prison sentence for an offense punished by the Revised Penal Code, or its amendments, the court shall sentence the accused to an indeterminate sentence the maximum term of which shall be that which, in view of the attending circumstances, could be properly imposed under the rules of the said Code, and the minimum which shall be within the range of the penalty next lower to that prescribed by the Code for the offense; and if the offense is punished by any other law, the court shall sentence the accused to an indeterminate sentence, the maximum term of which shall not exceed the maximum fixed by said law and the minimum shall not be less than the minimum term prescribed by the same.

[103] REVISED PENAL CODE, Article 63(3).

[104] Nacar v. Gallery Frames, 716 Phil. 267 (2013).

[105] Sec. 9. Penalties for violations. - (a) Any public officer or private person committing any of the unlawful acts or omissions enumerated in Sections 3, 4, 5 and 6 of this Act shall be punished with imprisonment for not less than six years and one month nor more than fifteen years, perpetual disqualification from public office, and confiscation or forfeiture in favor of the Government of any prohibited interest and unexplained wealth manifestly out of proportion to his salary and other lawful income.

[106] Supra note 95.




DISSENTING OPINION

CAGUIOA, J.:

I respectfully register my dissent.

I submit that petitioner Tito S. Sarion (petitioner) cannot and should not be convicted for violating Section 3(e) of Republic Act (R.A.) No. 3019, as amended, otherwise known as the Anti-Graft and Corrupt Practices Act, and the crime of Malversation of Public Funds or Property under Article 217 of the Revised Penal Code (RPC).

After a careful review of the facts of the case, it is crystal clear that petitioner cannot be convicted of the two crimes he was charged with.

Brief review of the facts

Petitioner was charged with violation of Section 3(e) of R.A. No. 3019, as amended, and Malversation of Public Funds, in two separate Informations, the accusatory portions of which read:

SB-11-CRM-0256

That on 24 April 2008 or sometime prior or subsequent thereto, in Daet, a first class municipality in the Province of Camarines Norte, Philippines, and within the jurisdiction of this Honorable Court, the accused, Tito S. Sarion, a public officer, being the Mayor of the Municipality of Daet, committing the crime in the discharge of his official functions, through manifest partiality, evident bad faith, or gross inexcusable negligence, did then and there willfully, unlawfully, and criminally cause undue injury to the government in the gross amount of One Million Pesos, Philippine Currency (PhP1,000,000.00), by then and there approving the disbursement in the absence of certificate of availability of funds, of public funds in said gross amount in favor of Markbilt Construction, the contractor for the construction of Daet Public Market (Phase II), as partial payment for its claim for price escalation which it is not entitled to so receive but which it received nevertheless per its Official Receipt No. 1156 dated 24 April 2008 through the approval of the disbursement voucher by the accused even without the approval from the Government Procurement Policy Board (GPPB) and the determination by the National Economic Deveiopment Authority (NEDA) as to the propriety of the claim for price escalation in violation of the GPPB Guidelines for Contract price Escalation to the prejudice of the Municipality of Daet in said amount.

CONTRARY TO LAW.

SB-11-CRM-0257

That on 24 April 2008, or sometime prior or subsequent thereto, in Daet, a first class municipality in the Province of Camarines Norte, Philippines, and within the jurisdiction of this Honorable Court, the accused, Tito S. Sarion, a public officer, being the Mayor of the Municipality of Daet, while in the performance of his official functions, committing the offense in relation to his office, and taking advantage of his official position, and in grave abuse thereof, having control of public funds in the gross amount of One Million Pesos, Philippine Currency (PhP1,000,000.00), which was placed under his administration by reason of the duties of his office, and is accountable for said amount of public funds pursuant to Section 340 of the Local Government Code, did then and there willfully, unlawfully and feloniously consent, or through abandonment or negligence, permit Markbilt Construction, the contractor for the construction of Daet Public Market (Phase II), to take such amount of public funds which it is not entitled to receive but which it received nevertheless per its Official Receipt No. 1156 dated 24 April 2008, by then and there allowing the disbursement through his approval of the disbursement voucher even in the absence of certificate of availability of funds in said gross amount in favor of Markbilt Construction as partial payment for its claim for the price escalation even without the approval from the Government Procurement Policy Board (GPPB) and the determination by the National Economic Development Authority (NEDA) as to the propriety of the claim for price escalation in violation of the GPPB Guidelines for Contract price Escalation.

CONTRARY TO LAW.[1] (Emphasis supplied)

The instant controversy arose from a Contract Agreement entered into on December 29, 2003 by herein petitioner, in his capacity as Municipal Mayor for the Municipal Government of Daet, Camarines Norte, and Mr. Billy Aceron (Aceron), General Manager of Markbilt Construction (Markbilt), represented by his attorney-in-fact, Architect Romeo B. Itturalde (Architect Itturalde).The agreement was for the Phase II construction of the Daet Public Market for the amount of P71,499,875.29, which was to be completed within a period of 365 calendar days.[2]

On January 5, 2005, petitioner approved a Notice to Commence Work authorizing Markbilt to commence with the construction project on the 10th day from receipt of said Notice. Thereafter, construction works proceeded. Meanwhile, petitioner's term ended and Elmer E. Panotes (Mayor Panotes) was elected as Municipal Mayor of Daet, Camarines Norte during the May 2004 national and local elections.[3]

The construction of the Daet Public Market was completed sometime in 2006. On November 13, 2006, the Office of Mayor Panotes received a letter from Markbilt, requesting the processing and payment of contract price escalation in the amount of P5,222,903.75, in relation to the Daet Public Market (Phase II) project. Mayor Panotes refused to act on the demand.[4]

During the local elections held in 2007, petitioner was re-elected as Mayor of the Municipality of Daet.[5] On January 21, 2008, in a letter addressed to petitioner, Markbilt reiterated its demand for payment of the contract price escalation.[6] A similar demand was made by Markbilt in a letter dated February 7, 2008, this time with the information that it would be imposing a 15% interest per annum on the claim.[7] Because of this demand, petitioner instructed Municipal Administrator Elmer Nagera (Administrator Nagera) to look for sources of funds to satisfy Markbilt's claim.[8] This gave rise to the creation of Supplemental Budget No. 1. After the same was signed by Municipal Budget Officer Amelia P. Laborte (Budget Officer Laborte) and approved by Administrator Nagera, Supplemental Budget No. 1 was submitted to the Sangguniang Bayan.[9]

On March 6, 2008, the Sangguniang Bayan passed Resolution No. 063 unanimously approving Supplemental Budget No. 1 and appropriating the amount of P11,222,088.00 of the municipality's internal revenue allotment. Of such amount, designated under the Special Account, P4,400,000.00 was allotted for the construction of market. Resolution No. 063 was later approved by petitioner.[10]

In another letter dated April 14, 2008, Markbilt reiterated its demand for payment of contract price escalation. After Budget Officer Laborte certified the existence of available appropriation, Administrator Nagera prepared Obligation Request No. 100-08-03-402 certifying that "the charges to appropriation/allotment are necessary, lawful and under his direct supervision" and that "the supporting documents are valid, proper and legal."[11] Subsequently, Administrator Nagera issued Disbursement Voucher No. 08041239 in the amount of P1,000,000.00 payable to Markbilt in partial satisfaction of its demand for contract price escalation.[12]

Concerned with the applicability of R.A. No. 9184, otherwise known as the "Government Procurement Reform Act," Municipal Accountant Caroline Maisie Robles (Accountant Robles) consulted the Commission on Audit (COA) Auditor assigned to the municipality, who in tum, advised her to seek the opinion of the Municipal Legal Officer. In his opinion, Municipal Legal Officer Edmundo Deveza II (Legal Officer Deveza) found, on the basis of Presidential Decree (P.D.) No. 1594,[13] that there was no reason to refuse the payment of obligation in favor of Markbilt. Thus, on April 21, 2008, Accountant Robles certified the supporting documents complete and the allotment for partial payment of Markbilt.[14] After Municipal Treasurer Arlyn O. Aberia certified that funds were available, petitioner approved the release of the funds for payment.[15] Thus, on April 24, 2008, Markbilt received payment of P1,000,000.00 made through Landbank Check No. 0272388, and evidenced by Official Receipt No. 1156 dated April 24, 2008.[16]

On June 17, 2008, the Sangguniang Panlalawigan of Camarines Norte, approved Resolution No. 229-2008 declaring as operative Supplemental Budget No. 1 of the Municipality of Daet.[17]

On November 27, 2008, Zenaida Baluca, a resident of Daet, Camarines Norte, filed a complaint against petitioner before the Deputy Ombudsman for Luzon.[18] The complainant charged petitioner with violation of Section 3(e) of R.A. No. 3019 relative to the payment of contract price escalation in the Daet Public Market (Phase II) Project.[19]

After investigation, Graft Investigation and Prosecution officer Judy Anne Doctor-Escalona found merit in the complaint and charged petitioner with violation of Section 3(e) of R.A. No. 3019, as amended, and Malversation of Public Funds, in two separate Informations.[20]

Petitioner was conditionally arraigned on September 2, 2011, and assisted by counsel, entered a plea of "not guilty."[21]

After trial, the Third Division of the Sandiganbayan rendered on September 29, 2017 the herein assailed Decision[22] finding petitioner guilty beyond reasonable doubt for violation of Section 3(e) of R.A. No. 3019 and Malversation of Public Funds.[23] The dispositive portion of the Decision reads:

WHEREFORE, this Court finds accused TITO S. SARION:

1.
Guilty beyond reasonable doubt of Violation of Section 3(e) of Republic Act No. 3019, and he is accordingly sentenced to:
     

a.
Suffer an indeterminate penalty of imprisonment of Six (6) years and One (1) month, as minimum, to Eight (8) years, as maximum, and,
     

b.
Suffer the penalty of perpetual special disqualification from holding public office; and,
   
2.
Guilty beyond reasonable doubt of Malversation of Public Funds or Property under Article 217 of the Revised Penal Code, and he is accordingly sentenced to:
     

a.
Suffer an indeterminate penalty of imprisonment of Two (2) years, Four (4) months and One (1) day of prision correccional, as minimum, to Six (6) years and One (1) of prision mayor, as maximum;
     

b.
Pay a fine in the amount of One Million Pesos (PhP1,000,000.00); and,
     

c.
Suffer the penalty of perpetual special disqualification from holding public office.

Accused Sarion shall indemnify the municipality of Daet the amount of One Million Pesos (PhP1,000,000.00) as actual damages, plus interest at the rate of 6% per annum to be reckoned from the date of finality of the Decision until full satisfaction.

SO ORDERED.[24]

Petitioner's Motion for Reconsideration was thereafter denied by the Sandiganbayan in its Resolution dated November 8, 2018.[25]

Thus, this petition for review on certiorari.[26]

In affirming the conviction of petitioner for the crime of Malversation of Public Funds, the ponencia rules that the prosecution was able to prove all of the elements of said crime:[27] (1) that petitioner is a public officer, being the then elected Municipal Mayor of Daet and that the funds involved are public in character, as they belong to the Municipality of Daet;[28] (2) that, by reason of his office, he is an accountable officer based on Section 340 of the Local Government Code, as well as P.D. No. 1445 or the Government Auditing Code of the Philippines;[29] (3) that the disbursement or release of funds had petitioner's approval as Mayor; and that payment in favor of Markbilt was released only after petitioner's signature in the disbursement voucher and the corresponding Landbank check;[30] and (4) agreeing with the Sandiganbayan, that petitioner was guilty of gross inexcusable negligence when he permitted Markbilt to receive partial payment of price escalation despite not being entitled thereto.[31]

The ponencia reasons that when petitioner signed the disbursement voucher in favor of Markbilt, he certified to the correctness of the entries therein, warranted that the expenses incurred were necessary and lawful, the supporting documents were complete, and the availability of cash therefor.[32] By approving the disbursement voucher and signing the Landbank check payable to Markbilt, despite the absence of funding and failure to comply with the requirements of Section 61,[33] R.A. No. 9184, petitioner permitted Markbilt to take public funds to which it is not entitled to.[34]

In affirming petitioner's conviction for violation of Section 3(e) of R.A. No. 3019, the ponencia again anchors this on the finding that petitioner is guilty of gross inexcusable negligence "amounting to bad faith."[35] The ponencia justifies its ruling on the following: (1) petitioner was remiss in his duty when he failed to exercise diligence in ensuring compliance with basic requirements demanded by the laws, rules, and regulations in the disbursement of public funds;[36] (2) as the signatory to the Contract Agreement with Markbilt, he is presumed to know the contents thereof;[37] thus (3) upon receipt of Markbilt's demand for price escalation, petitioner should have first verified the propriety of the said claim and whether the said claim satisfied the requirements of applicable laws.[38]

The ponencia likewise finds that the prosecution was able to prove the element of undue injury, as follows:[39] (1) petitioner's approval of the disbursement voucher and his signature in the Landbank check in favor of Markbilt facilitated the unauthorized release of P1,000,000.00 worth of public funds which belong to the Municipality of Daet,[40] (2) since Markbilt was not entitled to such payment, petitioner thus caused undue injury in this amount.[41]

I strongly disagree with the foregoing findings of the ponencia. To be sure, a careful review of the records shows that the foregoing findings are all belied by the evidence presented before the Sandiganbayan. I furthermore submit that following established jurisprudence, petitioner cannot be held guilty of "gross inexcusable negligence" for an act that was legal and fully compliant with the requirements of law. It is simply unjust to convict him; he should be acquitted of the crimes he is charged with.

While the Sandiganbayan Decision and the ponencia extensively discussed in relation to the crime of Malversation (1) the absence of Certificate of Availability of Funds (CAFs); and (2) petitioner's violation of the Government Procurement Policy Board (GPPB) Guidelines for Contract Price Escalation, and the absence of a determination by the National Economic Development Authority (NEDA) as to the propriety of the claim for price escalation, I likewise relate these discussions as far as applicable to R.A. No. 3019.

I.
Republic Act No. 3019

R.A. No. 3019, Section 3(e) reads:

SECTION 3. Corrupt practices of public officers.—In addition to acts or omissions of public officers already penalized by existing law, the following shall constitute corrupt practices of any public officer and are hereby declared to be unlawful:

x x x x

(e) Causing any undue injury to any party, including the Government, or giving any private party any unwarranted benefits, advantage or preference in the discharge of his official administrative or judicial functions through manifest partiality, evident bad faith or gross inexcusable negligence. This provision shall apply to officers and employees of offices or government corporations charged with the grant of licenses or permits or other concessions.

In order for an accused to be convicted under Section 3(e) of R.A. No. 3019, the prosecution must prove beyond reasonable doubt the following essential elements: (1) the accused must be a public officer discharging administrative, judicial or official functions; (2) he must have acted with manifest partiality, evident bad faith or inexcusable negligence; and (3) his action caused undue injury to any party, including the government, or gave any private party unwarranted benefits, advantage or preference in the discharge of his functions.[42]

I submit that the last two elements were not established at all.

Under existing case law, petitioner cannot be found to have committed gross inexcusable negligence

There are three modes of committing a violation under Section 3(e) of R.A. No. 3019, to wit:

x x x There is "manifest partiality" when there is a clear, notorious, or plain inclination or predilection to favor one side or person rather than another. "Evident bad faith" connotes not only bad judgment but also palpably and patently fraudulent and dishonest purpose to do moral obliquity or conscious wrongdoing for some perverse motive or ill will. "Evident bad faith" contemplates a state of mind affirmatively operating with furtive design or with some motive or self-interest or ill will or for ulterior purposes. "Gross inexcusable negligence" refers to negligence characterized by the want of even the slightest care, acting or omitting to act in a situation where there is a duty to act, not inadvertently but willfully and intentionally, with conscious indifference to consequences insofar as other persons may be affected.[43] (Emphasis supplied)

At the very outset, it should be emphasized that the Sandiganbayan found and held that petitioner did not commit manifest partiality, to wit.

Accused Sarion's approval of the payment for price escalation to Markbilt, without the requisite approval of the GPPB and NEDA's determination of the existence of extraordinary circumstances, does not necessarily imply manifest partiality on the part of the accused. Records do not show that accused Sarion favored Markbilt over another entity when he authorized the subject payment.[44] (Emphasis supplied)

The Sandiganbayan likewise held that petitioner did not act in evident bad faith, to wit:

The evidence is not sufficient to support a conclusion that accused Sarion was motivated by ill-will or dishonest purpose in paying Markbilt's demand for payment of contract price escalation. Accused Sarion appears to have relied on the legal opinion issued by the municipal legal officer which states: a) that P.D. No. 1594 is the applicable law in connection with Markbilt's claim for price escalation; b) The escalation prices were allegedly computed in accordance with the IRR of P.D. No. 1594; and c) There was no reason to refuse payment for price escalation. As concluded above, it appears that accused Sarion did not act in bad faith.[45] (Emphasis supplied)

The Sandiganbayan convicted petitioner on the belief that he acted with gross inexcusable negligence when he approved the payment of the price escalation in favor of Markbilt without confirming that it was lawfully entitled thereto.[46]

To recall, petitioner was charged under the Information for causing undue injury to the government because of his having approved the payment to Markbilt of P1,000,000.00, as partial payment for its claim for contract price escalation: (1) in the absence of CAFs; and (2) in violation of the GPPB Guidelines for Contract Price Escalation as the payment was made despite the absence of an approval from the GPPB, and in the absence of a determination by NEDA as to the propriety of the claim for price escalation.[47]

Thus, the only question is this: Were these acts of petitioner committed with gross inexcusable negligence?

The ponencia answers in the affirmative. The ponencia rules that petitioner was remiss in his duty when he failed to exercise diligence in "ensuring compliance with basic requirements demanded by the law, rules, and regulations in the disbursement of public funds."[48]

I disagree. This is plain manifest error.

I discuss these points ad seriatim.

First, it should be noted that the Information for violation of Section 3(e) of R.A. No. 3019 alleges that petitioner approved the disbursement "in the absence of certificate of availability of funds."[49] However, the Sandiganbayan found as a fact that there were CAFs, ruling only that there was an irregularity in the CAF:

The information charges accused Sarion of disbursing PhP1,000,000.00 in favor of Markbilt without a certificate of availability of funds. Disbursement Voucher No. 08041239 shows that Municipal Treasurer Arlyn Aberia certified to the availability of funds. Municipal Budget Officer Amelia P. Laborte certified, in the Obligation Request, to the existence of available appropriation. However, the certifications were irregular. Appropriation Ordinance No. 1 contained no appropriation for the payment of the amount of PhP1,000,000.00 to Markbilt. Appropriation Ordinance No. 1 shows that the appropriation was for the construction of the public market. There was no appropriation to pay for the contract price escalation, an obligation supposedly incurred in the already completed of the Daet Public Market.

Accused Sarion and his witnesses point to the deliberations of the Sangguniang Bayan. But the intent to pay the contract price escalation allegedly manifested during the deliberations are (sic) not reflected in Appropriation Ordinance No. 1. Notably, no documentary evidence was offered to prove the alleged deliberations.[50] (Emphasis supplied and underscoring in the original)

The Sandiganbayan further ruled:

Accused Sarion cannot blindly rely on the erroneous certification of his municipal budget officer that funds are available because he was the one who approved the Supplemental Budget Ordinance and it was clear that no appropriation for the contract price escalation was included therein. Nonetheless, the Court notes that the Information alleges the absence of, not the infirmity in, the certificate of availability of funds. Hence, the court cannot find him culpable for said action.[51] (Emphasis and underscoring supplied)

In spite of the Sandiganbayan's ruling that it cannot find petitioner culpable for the alleged irregularity in the CAF since "the Information alleges the absence of, not infirmity in, the [CAF],"[52] the ponencia nevertheless rules as follows:

An Information is sufficient when it states the designation of the offense and the acts or omissions which constitute the offense charged. The crime must be described in ordinary and concise language and with such particularity and reasonable certainty that the accused is duly informed of the offense charged and able to adequately prepare for his defense. "In particular, whether an Information validly charges an offense depends on whether the material facts alleged in the complaint or information shall establish the essential elements of the offense charged as defined in the law."

To recapitulate, Section 86 of P.D. No. 1445 requires the existence of a prior specific appropriation, as certified by the proper accounting official, before any contract for expenditure of public funds is authorized. In this sense, therefore, it is the absence of certification as to the availability of or source of funds pertaining specifically to the payment of price escalation, that rendered the clause void and the subsequent approval by the petitioner of the disbursement voucher invalid. It is this irregularity which rendered the payment in favor of Markbilt illegal. In turn, it is the transgression of the same basic principle in disbursement of public funds which translates to gross negligence on the part of the petitioner. With this, the elements of the offense sufficiently alleged and proven in the Information, there is no obstacle in convicting the petitioner of the crime of malversation.

At any rate, granting for the sake of argument that the failure of the Information to specifically employ the word "irregularity" instead of "absence" constitutes a violation of the petitioner's right to Information and as such may not be considered in determining the offenses charged, the petitioner may nonetheless be still be convicted of the crime of malversation and for violation of Section 3(e) of R.A. No. 3019 "through [his] approval of the disbursement voucher x x x even without the approval from the Government Procurement Policy Board (GPPB) and the determination by the National Economic Development Authority (NEDA) as to the propriety of the claim for price escalation in violation of the GPPB Guidelines for Contract Price Escalation," clearly stated and alleged in the two (2) Informations filed against him. x x x[53] (Emphasis and underscoring supplied)

The foregoing ruling violates petitioner's right, as an accused, to be properly informed of the charges against him.[54] As correctly pointed out by petitioner, he cannot be found guilty for an irregularity in the CAFs because this violates his right to be informed of the accusation against him under Section 14(1), Article III of the 1987 Constitution since the Information merely alleged the absence of CAFs, and not irregularity.[55] Stated differently, petitioner prepared for trial to prove, as he did, that there was a CAP. To convict him now on the reasoning that the CAP was "irregular" unduly deprived him the opportunity to directly traverse this.

More importantly, even the finding that there was an "irregularity" is wrong — it is completely belied by the evidence. This finding of "irregularity" in the CAF is based on the belief that "[t]here was no appropriation to pay for the contract price escalation."[56] The Sandiganbayan, as well as the ponencia, holds that Appropriation Ordinance No. 01[57] contained no appropriation for the payment of P1,000,000.00 to Markbilt.[58] At the point of being repetitive, this is just plain error.

The plain language of Supplemental Budget No. 1[59] belies this factual finding. To recall, Resolution No. 063 approved Supplemental Budget No. 1 for CY[60] 2008 for the Municipality of Daet. It was this Supplemental Budget No. 1[61] that was approved in Appropriation Ordinance No. 01. Stated simply, Appropriation Ordinance No. 01 approved each and every proposed item in Supplemental Budget No. 1, including the payment of P1,000,000.00 for the price escalation claim of Markbilt.[62] As correctly shown by petitioner:

The title of Resolution No. 063 is revealing as to what was approved by the Sangguniang Bayan, that is, Supplemental Budget No. 1, which contained an appropriation of P1,000,000.00 to partially pay Markbilt Construction's claim for price escalation –

Resolution Approving the Supplemental Budget No. 01 for CY 2008 for the Municipality of Daet Appropriating the Amount of Six Million Eight Hundred Twenty Two Thousand Eighty Eight Pesos (P6,822,088.00) for Various Municipal Projects/Expenditures under the General Fund Proper and for Special Account (Market) – Construction of Public Market Amounting to Four Million Four Hundred Thousand Pesos (P4,400,00.00) with a Total Amount of Eleven Million Two Hundred Twenty Two Thousand Eighty Eight Pesos (P11,222,088.00).[63]

Likewise, it is apparent in the title of Appropriation Ordinance No. 01 as to what was approved by the Sangguniang Bayan:

An Ordinance Approving the Supplemental Budget No. 01 for CY 2008 for the Municipality of Daet Appropriating the Amount of Six Million Eight Hundred Twenty Two Thousand Eighty Eight Pesos (P6,822,088.00) for Various Municipal Projects/Expenditures under the General Fund Proper and for Special Account (Market) – Construction of Public Market Amounting to Four Million Four Hundred Thousand Pesos (P4,400,00.00) with a Total Amount of Eleven Million Two Hundred Twenty Two Thousand Eighty Eight Pesos (P11,222,088.00).[64]

The portion of Appropriation Ordinance No. 01, which appropriated the amount of P4,400,000.00 as "Special Account (Market) Construction of Market" exactly corresponded to the appropriated items in that portion of Supplemental Budget No. 1 sub-marked as Exhibit 21-Q-1, which to repeat had these components:

Subsidy to Special Account – Market
Construction of Market 1,500,000.00
Price Escalation 1,000,000.00
Improvement/Repair Market 1,900,000.00[65]
   

These appropriated items would add up to P4,400,000.00, which is Exhibit 9-A-1 of the prosecution.

A cursory examination of Supplemental Budget No. 1 would show that the proposed appropriations therein were all approved and adopted in Appropriation Ordinance No. 01, as shown by the fact that Supplemental Budget No. 1 proposed a total appropriation of P11,222,088.00, which was the same approved amount in Appropriation Ordinance No. 01.

In other words, Appropriation Ordinance No. 01 approved each and every proposed item in Supplemental Budget No. 01, including the payment of P1,000,000.00 for the price escalation claim of Markbilt Construction.[66]

In other words, contrary to the findings of the Sandiganbayan and the ponencia, there was a valid appropriation to pay for the contract price escalation.

Accordingly, since there was a regularly issued CAF prior to petitioner's approval of the Disbursement Voucher, it is egregious error to still rule that petitioner acted with gross inexcusable negligence when he approved the Disbursement Vouchers.[67]

Second, on the alleged non-compliance with Section 61 of R.A. No. 9184, the evidence shows that: (1) the alleged non-compliance with Section 61 of R.A. No. 9184 did not pertain to petitioner; and (2) even assuming that compliance with Section 61 of R.A. No. 9184 pertained to petitioner, R.A. No. 9184 does not penalize the alleged irregularity.[68]

As correctly pointed out by petitioner, in the Notice of Disallowance[69] with ND No. 2010-001-101 (2008) dated March 17, 2010, the obligation to secure the documents required under Section 61 of R.A. No. 9184 did not pertain to petitioner, but to Architect Itturalde for Aceron –

Name Position/Designation Name of Participation in the Transaction
x x x x x x x x x
6. Romeo B. Itturalde For Mr. Billy Aceron Represented the General Manager, Billy Aceron Failure to submit the required documents in compliance to Section 61 of RA 9184.[70]

This is, in turn, fully corroborated by the admission of prosecution witnesses Jesus R. Reblora, Jr. (Reblora) and Lourdes G. Cribe (Cribe) that the obligation to submit the required documents in compliance with Section 61 of R.A. No. 9184 did not pertain to petitioner, but to Architect Itturalde for Aceron.[71]

On cross-examination, the COA Audit Team Leader,[72] Reblora, testified as follows:

Q:
Do you confirm that the representatives of Markbilt Construction namely: Romeo B. [Itturalde], Mr. A[c]eron, also appeared in the Notice of Disallowance?
   
A:
Yes, sir.
   
Q:
Now do you confirm also sir that in this entry regarding the nature of participation in the transaction of Romeo [Itturalde] of Mr. Billy A[c]eron or the representatives of Markbilt Construction, reads, "failure to submit the required documents in compliance to Section [6]1 of RA 9184," do you confirm that that is the nature of participation? (sic)
   
A:
Yes, sir.
   
Q:
Therefore, the alleged irregularity of the subject transaction which was [the] absence of that GPP[B] approval pertained to the representatives of Markbilt Construction per Notice of Disallowance, do you confirm that sir?
   
A:
That is part of the process.
   
Q:
My question is answerable by yes or no regarding this Notice of Disallowance that requirement belong[s] to Mr. Romeo [Itturalde] or Billy Aceron?
   
A:
Yes, sir.[73]

Cribe, who was the COA State Auditor V and Supervising Auditor who issued the Notice of Disallowance, likewise admitted that the failure to submit the required documents in compliance with Section 61 of R.A. No. 9184 did not appear in the line pertaining to petitioner:

Q:
Now, [I] show this Notice of Disallowance[,] do you confirm that this line here which reads and I quote, "failure to submit the required documents in compliance with Section 61 of R.A. 9184" does not appear in this line pertaining to Tito Sarion?


A:
It does not, sir.[74]

Moreover, even assuming that compliance with Section 61 of R.A. No. 9184 pertained to him, said law does not actually penalize the alleged irregularity.[75] R.A. No. 9184 does not contain a penal clause for not securing a GPPB and a NEDA clearance before payment of price escalation.[76]

In this relation, the Court held in Sabaldan, Jr. v. Ombudsman,[77] that violations of procurement laws do not ipso facto give rise to violation of R.A. No. 3019:

More importantly, it must be emphasized that the instant case involves a finding of probable cause for a criminal case for violation of Section 3(e) of R.A. No. 3019, and not for violation of R.A. No. 9184. Hence, even granting that there may be violations of the applicable procurement laws, the same does not mean that the elements of violation of Section 3(e) of R.A. No. 3019 are already present as a matter of course. For there to be a violation under Section 3(e) of R.A. No. 3019 based on a breach of applicable procurement laws, one cannot solely rely on the mere fact that a violation of procurement laws has been committed. x x x.[78] (Emphasis supplied)

Thus, in the recent case of Martel v. People,[79] (Martel) the Court ruled that in order to successfully prosecute the accused under Section 3(e) of R.A. No. 3019 based on a violation of procurement laws, the prosecution must prove beyond reasonable doubt that: (1) the violation of procurement laws caused undue injury to any party, including the government, or gave any private party unwarranted benefits, advantage or preference, and (2) the accused acted with evident bad faith, manifest partiality, or gross inexcusable negligence.

However, in the instant case, the Sandiganbayan conceded that petitioner did not act with evident bad faith or manifest partiality. Also, as previously discussed, the prosecution failed to prove that petitioner acted with gross inexcusable negligence. Thus, the second element is absent.

Further, as I stated in my Concurring Opinion in Villarosa v. People[80] (Villarosa), an accused should not be punished with imprisonment for violations of non-penal laws:

While I am in full agreement with the call to hammer the point that "public office is a public trust," I cannot, in good conscience, agree to punishing with imprisonment any and all violations of non-penal laws. It is true that public servants have a duty to know the limits of the authority granted to them. Yet, I cannot subscribe to the thinking that to do an act outside of those limits already constitutes "gross inexcusable negligence" that is criminally punishable. If that is the case, then we might as well dispense with administrative proceedings – whether in the Civil Service Commission or in the Ombudsman – against public officials, for what is the sense of having a distinction between administrative and criminal cases when every single misstep merits a criminal sanction.

It is also true that every person is presumed to know the law, and that ignorance of the law excuses no one from compliance therewith. However, it is likewise true that it is unjust to automatically punish someone with a criminal sentence by virtue of his non-compliance with a non-penal rule.[81] (Emphasis supplied and underscoring in the original)

Again, R.A. No. 9184 and R.A. No. 3019 are distinct laws with distinct requisites for their violation. A violation of one does not ipso facto result in a violation of the other.[82] Thus, even assuming that petitioner committed a violation of some provisions of R.A. No. 9184, he cannot and should not be convicted under R.A. No. 3019 without proof beyond reasonable doubt that the elements of a violation of R.A. No. 3019 are all present.

The ponencia insists that petitioner is "guilty of gross inexcusable negligence amounting to bad faith:"[83]

The Court affirms that the petitioner is guilty of gross inexcusable negligence amounting to bad faith. From the stated definition, there is gross inexcusable negligence when a public officer commits a breach of duty in a blatant and extremely careless manner; or when the violation of law is serious, flagrant, palpable, or there is willful indifference in complying with the same.

As previously discussed, the petitioner was remiss in his duty when he failed to exercise diligence in ensuring compliance with basic requirements demanded by the law, rules, and regulations in the disbursement of public funds. First, as the signatory in the Contract Agreement with Markbilt, he is presumed to know the contents thereof. On its face, the instrument only provides for a single appropriation for the construction project; there is no separate funding to support the contract price escalation clause therein. In the statement of the said clause, the parties covenant to comply with relevant rules and regulations with respect to the same. Albeit unnecessary, they explicitly incorporated the relevant guidelines with respect to adjustment of contract prices. Thus, upon receipt of Markbilt's demand for price escalation, prudence dictates for the petitioner to first verify the propriety of the said claim and whether the said claim satisfies the requirements of applicable laws. It is only then that the possibility of satisfying the claim can even be entertained. It is highly irregular and unusual to rely merely on the representation of the contractor as to the amount due, without validating whether the amount so claimed is accurate and correct. Likewise, it must be noted that petitioner was already confronted with Markbilt's demands for price escalation as early as January 21, 2008. Even so, there was no evidence on record of any effort on the part of the petitioner to direct municipal officials to inquire on the basis of Markbilt's claims vis-a-vis the Contract Agreement which is cited as basis therefor, when he had every opportunity to do so prior to release of Legal Officer Deveza's opinion and the preparation of the Supplemental Budget. This step could have easily alerted the petitioner or the municipal officials of the requirements of price escalation under the law, particularly that provided for under Sec. 61 of R.A. No. 9184.

Had the petitioner undertaken these steps, he would have realized, for reasons previously stated in this decision, that Markbilt's claim should be denied. The petitioner's failure to observe sufficient diligence under these circumstances which led to violation of the law and rules relating to disbursement of public funds amounts to gross inexcusable negligence.[84]

In this relation, it is important to stress first of all that gross inexcusable negligence does not mean evident bad faith. In my Concurring Opinion in Villarosa, I stated:

x x x "Section 3 (e) of RA 3019 may be committed either by dolo, as when the accused acted with evident bad faith or manifest partiality, or by culpa, as when the accused committed gross inexcusable negligence." In simple terms, "evident bad faith" entails willfulness to do something wrong, whereas "gross inexcusable negligence" entails failure to exercise the required diligence that either results in a wrong or in the failure to prevent the occurrence of a wrongdoing. Thus, "gross inexcusable negligence" and "evident bad faith" are separate and distinct from each other. x x x[85] (Emphasis supplied and italics in the original)

Felonies committed by means of dolo or deceit are those performed with deliberate intent. On the other hand, felonies committed by means of culpa are those performed with imprudence, negligence, lack of foresight, or lack of skill.[86] In intentional felonies, the act or omission of the offender is malicious. However, in culpable felonies, the act or omission of the offender need not be malicious. The wrongful act results from imprudence, negligence, lack of foresight or lack of skill.[87]

Gross inexcusable negligence under Section 3(e) of R.A. No. 3019 does not require fraudulent intent or ill-will. A public officer is guilty of gross inexcusable negligence when there is a breach of duty that is committed flagrantly, palpably, and with willful indifference.[88] Hence, a public officer who seriously breaches his or her duty in a blatant and extremely careless manner is guilty of gross inexcusable negligence under Section 3(e).

To stress anew, as held in Martel:

The commission of Section 3(e) of R.A. 3019 through gross inexcusable negligence requires more than simple negligence. The negligence committed must be both gross and inexcusable, characterized by the want of even slight care, wherein the accused was consciously indifferent as to the compliance with his or her duty as a public officer. More than committing a breach of a legal duty, it is necessary that in committing the said breach, the public officer was inattentive, thoughtless, and careless.[89] (Emphasis and underscoring supplied; italics in the original)

On this score, the following arguments of petitioner are well-taken:

The Municipal Legal Officer was competent to determine the applicable law insofar as the claim was concerned. The Municipal Accountant and the Municipal Mayor were not lawyers. They could not be faulted for relying on the legal opinion of the Municipal Legal Officer who was presumed to know the correct law.

Thus, Tito Sarion rightfully and lawfully relied in good faith on the acts of the other municipal officers who verified the regularity of the transaction.

There being no patent irregularity and considering that the transaction had gone through the proper procedure as certified by the officers concerned, Tito Sarion finally gave his approval to the Disbursement Voucher.

Negligence is the omission to do something which a reasonable man guided by those considerations, which ordinarily regulate the conduct of human affairs, would do, or the doing of something which a prudent and reasonable man would do.

To convict Tito Sarion for an act which appears to be perfectly valid and after due regard to the conduct and performance of duty of other municipal officers before him, is patently unjust and arbitrary.[90]

The records show that petitioner signed on the basis of the acts of the other municipal officers who verified the regularity of the transaction.[91] All concerned municipal officers, including Accountant Robles and petitioner, relied on the legal opinion of Legal Officer Deveza.[92] In fact, petitioner did not only sign on the basis of the legal opinion of the Legal Officer, but he also relied on all the certifications and approvals of all concerned local officials including the presumed validity of Appropriation Ordinance No. 01 that approved the Supplemental Budget No. 1, which included a P1,000,000.00 appropriation for Markbilt Construction.[93] Thus, petitioner's actions cannot be characterized as one where he acted without even the slightest care.

In this regard, the ponencia insists that petitioner should have taken steps to verify the propriety of the said claim and whether the said claim satisfies the requirements of applicable laws.[94] The ponencia further rules that when there are circumstances that should have alerted heads of offices to exercise a higher degree of circumspection in the performance of their duties, they cannot invoke the doctrine to escape liability.[95] In this scenario, heads of offices are expected to exercise more diligence and go beyond what their subordinates have prepared.[96]

With all due respect, under the factual milieu of this case, the evidence shows that petitioner did exercise the required diligence. The fault ascribed to him by the ponencia simply does not exist, viz.:

x x x Even so, there was no evidence on record of any effort on the part of the petitioner to direct municipal officials to inquire on the basis of Markbilt's claims vis-a-vis the Contract Agreement which is cited as basis therefor, when he had every opportunity to do so prior to release of Legal Officer Deveza's opinion and the preparation of the Supplemental Budget. This step could have easily alerted the petitioner or the municipal officials of the requirements of price escalation under the law, particularly that provided for under Sec. 61 of R.A. No. 9184.[97]

The fact remains that Legal Officer Deveza gave his legal opinion that the demand of Markbilt should be paid. For petitioner to be labelled as negligent for not "direct[ing] municipal officials [to direct municipal officers] to inquire on" Markbilt's demands "prior to release of" Legal Officer Deveza's opinion is, with respect, nonsensical. Again, the fact is that Legal Officer Deveza gave his imprimatur to the payment.

Moreover, the ponencia utterly fails to even state what circumstances it is referring to that should have "alerted [petitioner] to exercise a higher degree of circumspection."[98]

In this regard, petitioner's reliance on Arias v. Sandiganbayan[99] is very apropos:

We would be setting a bad precedent if a head of office plagued by all too common problems – dishonest or negligent subordinates, overwork, multiple assignments or positions, or plain incompetence – is suddenly swept into a conspiracy conviction simply because he did not personally examine every single detail, painstakingly trace every step from inception, and investigate the motives of every person involved in a transaction before affixing his signature as the final approving authority.

x x x x

We can, in retrospect, argue that Arias should have probed records, inspected documents, received procedures, and questioned persons. It is doubtful if any auditor for a fairly sized office could personally do all these things in all vouchers presented for his signature. The Court would be asking for the impossible. All heads of offices have to rely to a reasonable extent on their subordinates and on the good faith of those prepare bids, purchase supplies, or enter into negotiations. If a department secretary entertains important visitors, the auditor is not ordinarily expected to call the restaurant about the amount of the bill, question each guest whether he was present at the luncheon, inquire whether the correct amount of food was served, and otherwise personally look into the reimbursement voucher's accuracy, propriety, and sufficiency. There has to be some added reason why he should examine each voucher in such detail. Any executive head of even small government agencies or commissions can attest to the volume of papers that must be signed. There are hundreds of documents, letters, memoranda, vouchers, and supporting papers that routinely pass through his hands. The number in bigger offices or departments is even more appalling.

There should be other grounds than the mere signature or approval appearing on a voucher to sustain a conspiracy charge and conviction.[100] (Emphasis and underscoring supplied; italics in the original)

Likewise, in Sistoza v. Desierto,[101] the Court held:

There is no question on the need to ferret out and expel public officers whose acts make bureaucracy synonymous with graft in the public eye, and to eliminate systems of government acquisition procedures which covertly ease corrupt practices. But the remedy is not to indict and jail every person who happens to have signed a piece of document or had a hand in implementing routine government procurement, nor does the solution fester in the indiscriminate use of the conspiracy theory which may sweep into jail even the most innocent ones. To say the least, this response is excessive and would simply engender catastrophic consequences since prosecution will likely not end with just one civil servant but must, logically, include like an unsteady streak of dominoes the department secretary, bureau chief, commission chairman, agency head, and all chief auditors who, if the flawed reasoning were followed, are equally culpable for every crime arising from disbursements they sanction.

Stretching the argument further, if a public officer were to personally examine every single detail, painstakingly trace every step from inception, and investigate the motives of every person involved in a transaction before affixing his signature as the final approving authority, if only to avoid prosecution, our bureaucracy would end up with public managers doing nothing else but superintending minute details in the acts of their subordinates. x x x[102] (Emphasis and underscoring supplied)

Thus, there being no "irregularity" in the CAF, or any other patent irregularity in the transaction that had gone through the proper procedure as certified by the officers concerned before petitioner signed the disbursement voucher, as well as the fact that petitioner relied on a legal opinion, it is erroneous to insist that petitioner is guilty of gross inexcusable negligence, more so that he acted in bad faith.

There were no unwarranted benefits, advantage, or preference given to Markbilt nor any undue injury to the government

The ponencia, in upholding the Sandiganbayan ruling that the prosecution was able to prove the element of undue injury to the government,[103] refers solely to the absence of a GPPB approval and the absence of a determination by NEDA as to the propriety of the claim for price escalation.[104]

However, as previously discussed, the evidence unequivocally established that: (1) there was indeed an appropriation to pay for the contract price escalation; (2) the alleged non-compliance with Section 61 of R.A. No. 9184 did not pertain to petitioner; and (3) even assuming that compliance with Section 61 of R.A. No. 9184 pertained to petitioner, the same law does not penalize the alleged irregularity.[105] Finally, there is no question that work was actually done by Markbilt.

To still hold that petitioner gave unwarranted benefits, advantage or preference to Markbilt is to contradict established jurisprudence because it was not proven that petitioner acted with corrupt intent. In Martel, the Court held:

x x x As its title implies, and as what can be gleaned from the deliberations of Congress, R.A. 3019 was crafted as an anti-graft and corruption measure. At the heart of the acts punishable under R.A. 3019 is corruption. As explained by one of the sponsors of the law, Senator Arturo M. Tolentino, "[w]hile we are trying to penalize, the main idea of the bill is graft and corrupt practices. x x x Well, the idea of graft is the one emphasized." Graft entails the acquisition of gain in dishonest ways.[106] (Italics and underscoring in the original)

Further, as I stated in my Concurring Opinion in Villarosa:

Hence, in saying that a public officer gave "unwarranted benefits, advantage or preference," it is not enough that the benefits, advantage, or preference was obtained in transgression of laws, rules, and regulations. Such benefits must have been given by the public officer to the private party with corrupt intent, a dishonest design, or some unethical interest. This is in alignment with the spirit of RA 3019, which centers on the concept of graft.

I recognize that this is not the understanding under the current state of jurisprudence. Jurisprudence has defined the term "unwarranted" as simply lacking adequate or official support; unjustified; unauthorized or without justification or adequate reason. "Advantage" means a more favorable or improved position or condition; benefit, profit or gain of any kind; benefit from some course of action. "Preference" signifies priority or higher evaluation or desirability; choice or estimation above another. The term "private party" may be used to refer to persons other than those holding public office, which may either be a private person or a public officer acting in a private capacity to protect his personal interest.

Thus, under current jurisprudence, in order to be found guilty for giving any unwarranted benefit, advantage, or preference, it is enough that the public officer has given an unauthorized or unjustified favor or benefit to another, in the exercise of his official, administrative or judicial functions. By giving any private party unwarranted benefit, advantage, or preference, damage is not required. It suffices that the public officer has given unjustified favor or benefit to another in the exercise of his official functions. Proof of the extent or quantum of damage is not even essential, it being sufficient that the injury suffered or benefit received could be perceived to be substantial enough and not merely negligible.

I respectfully submit, and evidently the majority agrees, that it is high time for the Court to revisit this line of reasoning.

The foregoing understanding of "unwarranted benefit, advantage, or preference" is too broad that every single misstep committed by public officers that result in benefits to private parties falls under the definition and would thus possibly be criminally punishable. Every little error no matter how minor- would satisfy the fourth element as the threshold is simply that the benefit be "unjustified," "unauthorized," or "without justification." For instance, a contract awarded in good faith based on an interpretation of the law that would later on be judicially declared incorrect would be sufficient basis for affirming the existence of the fourth element, which may lead to the incarceration of a public officer simply because a private party received a benefit "without justification," yet was revealed to be so only in hindsight.

While it is true that public office is a public trust, the Court is called upon to likewise play its part in not interpreting the laws to effectively be a disincentive to individuals in joining the public service. It is simply absurd to criminally punish every minute mistake that incidentally caused a benefit to private parties even when these acts were not done with corrupt intent.

In the instant case, for example, Villarosa's act of issuing the extraction permits was motivated, not by any corrupt intent to favor one operator over another or to unduly receive any pecuniary benefit. Based on the evidence, his actuations were simply based on his honest belief that he had the authority to issue the permits. To be sure, the evidence in fact shows that all the pertinent taxes and fees in the issuance of the said permits were collected, creating revenue for the provincial government, the municipality, and the barangay. No pecuniary benefit went to the wrong person or entity – in other words, the evidence clearly showed that no graft and corruption actually transpired.[107] (Emphasis supplied and italics in the original)

To show that petitioner did not act with corrupt intent, a dishonest design, or some unethical interest, the following arguments of petitioner are very telling:

The Contract Agreement between Markbilt Construction and the Municipality of Daet x x x contained a provision of price escalation.

Invoking such provision, Markbilt Construction sent five (5) demand letters, from 2005 to 2008, for the payment of its price escalation claim x x x. Plaintiff's witness, Jesus R. Reblora, Jr., confirmed the existence of these demand letters.

With its previous demand letters being ignored by the municipality, Markbilt Construction sent another demand letter dated 7 February 2008 x x x charging the municipality a fifteen percent (15%) interest per annum on its P5.2 million price escalation claim and threatening to sue the municipality.

Tito Sarion did not want the municipal government to be dragged into an expensive lawsuit so he referred these demand letters to the Sangguniang Bayan.

The Sanggunian acted upon the claim made by Markbilt Construction by enacting an appropriation. The payment did not even pass through Tito Sarion, who did not receive any benefit or commission from such payment.

His act did not cause undue injury to the Municipality of Daet. In fact, such act redounded to its benefit.

Only then that the Disbursement Voucher x x x was prepared by the Municipal Accountant who certified as to the existence of an allotment for the purpose and the completeness of supporting documents. In same Disbursement Voucher, the Municipal Treasurer certified on the availability of funds. Only after such certifications by the said municipal officers did Tito Sarion, as Municipal Mayor, sign the Disbursement Voucher.[108] (Emphasis and underscoring supplied)

Thus, in the instant case, similar to Villarosa and Martel, it cannot be said that petitioner acted with corrupt intent.

As previously discussed, petitioner relied in good faith on the acts of the other municipal officers who verified the regularity of the transaction. In fact, the Sandiganbayan concededly admitted that petitioner did not act in bad faith because the evidence presented by the prosecution was not sufficient to support a conclusion that petitioner was motivated by ill-will or dishonest purpose in paying Markbilt's demand for payment of contract price escalation having relied on the legal opinion issued by the municipal legal officer.[109]

The Sandiganbayan further held that petitioner relied on the legal opinion issued by the municipal legal officer which states: (a) P.D. No. 1594 is the applicable law in connection with Markbilt's claim for price escalation; (b) the escalation prices were allegedly computed in accordance with the Implementing Rules and Regulations of P.D. No. 1594; and (c) there was no reason to refuse payment for price escalation.[110] In the face of all these, as recognized by the Sandiganbayan itself, it is clear that petitioner was justified in his acts by his honest belief that there were no irregularities in the payment of the escalation prices to Markbilt.

In sum, the second and third elements of a violation of Section 3(e) of R.A. No. 3019 do not exist. This warrants the acquittal of petitioner for the charge of violation of Section 3(e) of R.A. No. 3019.

II.
Malversation of Public Funds or Property
under Article 217 of the RPC

Article 217 of the RPC defines and penalizes Malversation of Public Funds as follows:

Art. 217. Malversation of public funds or property. — Presumption of malversation.—Any public officer who, by reason of the duties of his office, is accountable for public funds or property, shall appropriate the same, or shall take or misappropriate or shall consent, through abandonment or negligence, shall permit any other person to take such public funds or property, wholly or partially, or shall otherwise be guilty of the misappropriation or malversation of such funds or property x x x[.]

In order to convict an accused for Malversation of Public Funds, the prosecution must prove beyond reasonable doubt the following elements: (a) that the offender is a public officer; (b) that he had custody or control of funds or property by reason of the duties of his office; (c) that those funds or property were public funds or property for which he was accountable; and (d) that he appropriated, took, misappropriated or consented, or through abandonment or negligence, permitted another person to take them.

From the earlier disquisition, it is clear that the fourth element was shown to not exist.

In fine, it simply cannot be said that petitioner permitted Markbilt to take the P1,000,000.00 "through abandonment or negligence."

In this regard, the ponencia holds that petitioner, through gross inexcusable negligence, permitted Markbilt to receive partial payment of price escalation despite not being entitled thereto.[111] The ponencia rules:

x x x Thus, when petitioner signed the disbursement voucher in favor of Markbilt, in effect, he certified to the correctness of the entries therein; and warranted that the expenses incurred were necessary and lawful, the supporting documents were complete, and the availability of cash therefor. By approving the disbursement voucher and signing the Landbank check payable to Markbilt, despite the absence of funding and failure to comply with the requirements of Section 61, R.A. No. 9184, he permitted Markbilt to received (sic) public funds to which it is not entitled. Otherwise, the petitioner's approval and signature in respect facilitated the illegal release of funds, constitutive of the act of malversation.[112] (Emphasis supplied)

Again, it is without doubt that there was a CAF; meaning that there was a funding.[113]

It has also already been shown that the obligation to secure the documents required under Section 61 of R.A. No. 9184 did not pertain to petitioner, but to Architect Itturalde for Aceron.[114] As well, it was established that the acts of petitioner cannot be said to have been with a total want of care.

With the absence of the fourth element of the crime of Malversation of Public Funds, petitioner should be acquitted.

Presumption of Innocence

On a final note, I would like to stress the constitutionally enshrined principle of presumption of innocence, fleshed out by procedural rules which place on the prosecution the burden of proving that an accused is guilty of the offense charged by proof beyond reasonable doubt.[115] Absolute guarantee of guilt is not demanded by the law to convict a person of a criminal charge but there must, at least, be moral certainty on each element essential to constitute the offense and on the responsibility of the offender.[116] Thus, the prosecution has the primordial duty to present its case with clarity and persuasion, to the end that conviction becomes the only logical and inevitable conclusion.[117]

In the instant case, since the prosecution failed to prove beyond reasonable doubt the guilt of petitioner for violation of Section 3(e) of R.A. No. 3019 and Malversation of Public Funds, the presumption of innocence of petitioner must be upheld.

Thus, I respectfully dissent. I accordingly vote that petitioner be acquitted of the crimes charged.


[1] Ponencia, pp. 4-5.

[2] Id. at 1-2.

[3] Id. at 2.

[4] Id.

[5] Id.

[6] Id.

[7] Id.

[8] Id.

[9] Id. at 3.

[10] Id.

[11] Id.

[12] Id.

[13] PRESCRIBING POLICIES, GUIDELINES, RULES AND REGULATIONS FOR GOVERNMENT INFRASTRUCTURE CONTRACTS, approved on June 11, 1978.

[14] Ponencia, pp. 3-4.

[15] Id. at 4.

[16] Id.

[17] Id.

[18] Id.

[19] Id.

[20] Id.

[21] Id. at 5.

[22] Rollo, pp. 95-119-A. Penned by Associate Justice Sarah Jane T. Fernandez with Presiding Justice Amparo M. Cabotaje-Tang and Associate Justice Bernelito R. Fernandez, concurring.

[23] Ponencia, pp. 5-6.

[24] Rollo, pp. 118-A-119.

[25] Ponencia, p. 7.

[26] Rollo, pp. 11-90.

[27] See ponencia, pp. 9-11.

[28] Id. at 10.

[29] Id.

[30] Id. at 10-11.

[31] Id. at 11.

[32] Id.

[33] SEC. 61. Contract Prices. — For the given scope of work in the contract as awarded, all bid prices shall be considered as fixed prices, and therefore not subject to price escalation during contract implementation, except under extraordinary circumstances and upon prior approval of the GPPB.

For purposes of this Section, "extraordinary circumstances" shall refer to events that may be determined by the National Economic and Development Authority in accordance with the Civil Code of the Philippines, and upon the recommendation of the procuring entity concerned.

[34] Ponencia, p. 11.

[35] Id. at 21.

[36] Id.

[37] Id.

[38] Id.

[39] Id. at 22.

[40] Id.

[41] Id.

[42] Rivera v. People, G.R. No. 228154, October 16, 2019, accessed at <https://elibrary.judiciary.gov.ph/ thebookshelf/showdocs/1/65819>.

[43] Tiongco v. People, G.R. Nos. 218709-10, November 14, 2018, 885 SCRA 480, 507.

[44] Rollo, pp. 117-117-A.

[45] Id. at 117-A.

[46] Id.

[47] Id. at 72-73. Information for SB-11-CRM-0256.

[48] Ponencia, p. 21.

[49] Id. at 4; emphasis and italics supplied.

[50] Rollo, pp. 47-48.

[51] Id. at 112.

[52] Id.

[53] Ponencia, pp. 15-16.

[54] Rollo, p. 47.

[55] Id.

[56] Id. at 112.

[57] Spelled "Appropriation Ordinance No. 1" in some parts of the rollo.

[58] Id; ponencia, p. 15.

[59] Rollo, p. 48.

[60] Calendar Year.

[61] Rollo, pp. 49-50.

[62] Id. at 50-51.

[63] See Exhibit 21-Q, id. at 49.

[64] Exhibit 9, id. at 24.

[65] Exhibit 21-Q-1, id. at 49.

[66] Rollo, pp. 50-51.

[67] Ponencia, p. 11.

[68] Rollo, p. 52.

[69] Exhibit 20, id.

[70] Id.

[71] Rollo, pp. 53-54.

[72] Id. at 16.

[73] Id. at 53.

[74] Id. at 53-54.

[75] Id. at 54.

[76] Id.

[77] G.R. No. 238014, June 15, 2020, accessed at <https://elibrary.judiciary.gov.ph/thebookshelf/show docs/1/66254>.

[78] Id.

[79] G.R. Nos. 224720-23 & 224765-68, February 2, 2021.

[80] G.R. Nos. 233155-63, June 23, 2020, accessed at <https://elibrary.judiciary.gov.ph/thebookshelf/ showdocs/1/66280>.

[81] Id.

[82] Sabaldan, Jr. v. Ombudsman, supra note 77.

[83] Ponencia, p. 21; emphasis and italics supplied.

[84] Id. at 21-22.

[85] Supra note 80.

[86] Act No. 3815, as amended, otherwise known as the REVISED PENAL CODE, Art. 3.

[87] Calimutan v. People, G.R. No. 152133, February 9, 2006,482 SCRA 44, 66, citing Luis B. Reyes, THE REVISED PENAL CODE (13th Ed., 1993), pp. 33-34.

[88] Sistoza v. Desierto, G.R. No. 144784, September 3, 2002, 388 SCRA 307, 316.

[89] Supra note 79, at 27.

[90] Rollo, p. 85.

[91] Id.

[92] Id. at 83.

[93] Id. at 61.

[94] See ponencia, pp. 18-20.

[95] Id. at 18.

[96] Id.

[97] Id. at 21-22.

[98] Id. at 18.

[99] G.R. Nos. 81563 & 82512, December 19, 1989, 180 SCRA 309.

[100] Id. at 315-316.

[101] Supra note 88.

[102] Id. at 315-316.

[103] Ponencia, p. 22; rollo, p. 118.

[104] Rollo, p. 118.

[105] Id. at 52.

[106] Supra note 79, at 29.

[107] Supra note 80.

[108] Rollo, pp. 87-88.

[109] Id. at 117-A.

[110] Id.

[111] Ponencia, p. 11.

[112] Id.

[113] See supra note 49-67.

[114] See supra note 70-74.

[115] People v. Maraorao, G.R. No. 174369, June 20, 2012, 674 SCRA 151, 160.

[116] People v. Jampas, G.R. No. 177766, July 17, 2009, 593 SCRA 241, 256.

[117] Id.