(NAR) VOL. 15 NOS. 3-4 / JULY - SEPTEMBER 2004

[ ERC, December 15, 2003 ]

AMENDMENT TO THE SCHEDULE OF ERC FEES AND CHARGES



This revised schedule of rates which was approved by the Commission at its meeting held on 03 December 2003 amends Item IV-A of the Schedule of ERC Fees and Charges to read as follows:

NATURE OF FEES

LEGAL BASIS
AMOUNT OF FEES
   
IV-A For the issuance of Certificate of Compliance (COC) to Independent Power Producer (for 5 years duration) pursuant to the standards set for the generation of electric power.
Section 6 R.A. No. 9136
Php 10,000.00 (exclusive of actual cost a technical audit/evaluation)
 
 
IV-B For the issuance of Certificate of Compliance (COC) to the owner of a Self Generation Facilities with the following aggregate installed capacity (for 5 years duration) pursuant to the standards set for the generation of electric power:
Section 6 R.A. No. 9136
 
   
100 KW and below



 Php 1,500.00 (exclusive of actual cost for a technical audit/evaluation)
   
101 - 500 KW
 Php 5,000.00 (exclu- of actual cost for a technical audit/evaluation)
   
501 - 999 KW
 Php 7,500.00 (exclusive of actual cost for a technical audit/evaluation)
   
1 MW and above
 Php 10,000.00 (exclusive of actual cost for a technical audit/evaluation)


This amendment to the Schedule of ERC Fees and Charges shall become effective fifteen (15) days following its publication in a newspaper of general circulation.

Adopted: 15 Dec. 2003
 

(SGD.) MANUEL R. SANCHEZ

Chairman
(SGD.) OLIVER B. BUTALID
(SGD.) CARLOS R. ALINDADA
Commissioner
Commissioner
(SGD.) LETICIA V. IBAY
(SGD.) JESUS N. ALCORDO
Commissioner
Commissioner


Source: Supreme Court E-Library
This page was dynamically generated
by the E-Library Content Management System (E-LibCMS)