(NAR) VOL. 14 NOS. 1-2 / JANUARY - MARCH 2003
I. Breakbulk/Bulk Cargoes
a) Incoming -One (1) Calendar Day after the day the cargo is discharged from the carrying vessel. b) Outgoing -Two (2) Calendar Days prior to the day that the carrying vessel is scheduled to arrived. c) Shut-out -Two (2) Calendar Days after vessels departure.
II. Containers
a) In-Loaded - One (1) Calendar Day after the day the container isdischarged.b) In-Empty - One (1) Calendar Day from day of discharge.c) Out-Loaded - Two (2) Calendar Days prior to the day that the carrying vessel is scheduled to arrive.d) Out-Empty - Two (2) Calendar Days prior to the day that the carrying vessel is scheduled to arrive.e) Stripped Containers - One (1) Calendar Day after stripping.f) Shut-Out - Two (2) Calendar Days after vessel's departure.g) Loaded Containers coming from outside the Port Areas - Two (2) Calendar Days prior to the day that the carrying vessel is scheduled to arrive.
This Circular shall take effect fifteen (15) days after publication.
For guidance and strict compliance.
Adopted: January 23, 2003
(SGD.) MARIANO C. J. MARTINEZ
General Manager