1.1 | For actual field survey work, the amount to be charged for each lot of original isolated and advance surveys shall be computed using the following formula: |
C = P= 11.00 multiplied by N + P = 5.00 multiplied by the square root of A |
1.2 | The amount to be charged for relocation surveys, field verification surveys or resurveys shall be one hundred sixty per cent (160%) of the amount computed on the basis of the formula in Paragraph 1.1 but in no case shall the charge for each lot be less that Six Hundred Sixty (P660.00) Pesos. In case the Geodetic Engineer is required to testify in Court on the results of survey, the party/parties in interest shall defray the traveling and other official expenses of the Geodetic Engineer by depositing with the DENR-LMS the necessary amount to cover actual expenses. |
1.3 | The amount to be charged for each of the lots into which an original survey is subdivided in the case of a complete subdivision or consolidation-subdivision survey shall be sixty five (65%) percent of the amount computed using the formula in Paragraph 1.1 provided, that the total charge shall in no case be less than Six Hundred Sixty (P660.00) Pesos. |
1.4 | The amount to be charged for development surveys such as topographic surveys and others, when the elevation is reckoned from an assumed datum or when a bench mark is near the site, and the contour interval is less than one (1) meter, shall be in accordance with the following rates: |
For the first hectare or fraction thereof-P1,650.00 For the 2nd to 10th hectares an additional 450.00/ha. For the 11th to 20th hectares, an additional 400.00/ha. For the 21st to 30th hectares, an additional 350.00/ha. For the 31st to 50th hectares, an additional 300.00/ha. In excess of 50 hectares, an additional 250.00/ha. | |
If true elevation is required, additional cost shall be charged for the connecting level circuit from an established bench mark. For contour interval of less than one (1) meter, charges shall be based on actual cost. | |
1.5 | The charges for all other surveys and special surveys not included in the foregoing paragraphs shall be computed based on actual cost. The charges shall cover actual cost which shall depend on the project specifications, methods of work, location, local conditions and other work parameters. |
1.6 | In the foregoing paragraphs and in all cases in this Order where it becomes applicable, (a) any common corner shall be counted as many times as there are lots to which it pertains, and (b) a fraction of a hectare shall be considered one hectare. |
3.1 For the ocular field inspection of the public land subject of a request for survey authority; or of land covered by public land survey, or of other isolated survey whose field inspection is deemed necessary, the charge in lieu of the cash deposit required in Section 10-12, Lands Administrative Order No. 4 dated 3 July 1980 shall beField inspection deposit = P11.00 H + 1.00 K + P110 but in no case shall the charge be less than P200;
T = | contract period, in days |
P = | Estimated number of parcels in the project subject to adjustment after final survey on the basis of increase of the number of lots |
3.3 | The amount to be charged for the field inspection on the setting of corner monuments of subdivision projects within the purview of P.D. 957 (Subdivision and Condominium Buyer's Protective Decree) for purpose of office verification and/or approval shall be: |
a) For each project or project phase with an aggregate area of 1,000 sq. m. or less P165.00 | |
b) For each project phase with an aggregate area of more than 1,000 square meters | |
1) For the first 1,000 sq. m. - P165.00 | |
2) For every succeeding 1,000 sq. m. or fraction thereof - P22.00 |
4.1 | Verification of Isolated Surveys - Verification of survey returns submitted by private practitioners for land registration proceedings, patent issuance and for other purposes: |
4.1.1 | Original Surveys |
a) For each parcel/lot P6.00 | |
b) Plus for each lot corner 0.50 | |
c) Plus for each traverse station 0.20 | |
d) Plus for each solar/stellar observation 2.00 | |
but in no case shall the charge per survey be less than TWENTY (P20.00) Pesos. | |
4.1.2 | Subdivision Surveys |
In the case of complete subdivision of previously approved surveys the verification fees shall be at the rate of sixty per cent (60%) of what would be charged if the subdivision survey were an original survey. | |
In the case of segregation surveys, the fees shall be the same as for original surveys in Paragraph 4.1.1. | |
In every case, each lot and its corresponding number of corners shall be considered independently in to computation of the fees. | |
4.1.3 | The rates of fees prescribed in Paragraph 4.1.1 shall also apply to the examination, verification, approval of consolidation, consolidation-subdivision, resubdivision and reconsolidation plans. |
4.1.4 | In the computation of fees relative to lots subject of consolidation and consolidation-subdivision plans, a fee of three (P3.00) pesos shall be collected per lot as appearing into original survey in addition to the fee collectible in Paragraph 4.1.1 for the new lots. |
4.1.5 | For the verification and approval of a tracing cloth plan as part of the survey returns a fee of six (P6.00) pesos shall be charged. |
4.2.1 | For copies of plans of previously approved surveys prepared and submitted by licensed Geodetic Engineers in the private practice for verification and certification, the charges are: |
For the first 20 corners — P8.00 | |
For each additional corner over 20 corners — 0.20 |
4.2.2 | For typewritten technical descriptions of previously approved surveys submitted for verification and certification, the charges are: |
For the first page — P6.00 | |
For each additional page — 1.00 | |
4.2.3 | For verification and certification of lot descriptions prepared on tracing cloth form (in tabulated format), the charge is: |
For each sheet — P6.00 |
a) For each page — P12.00In the case of a cadastral lot, the proportionate cadastral cost shall also be collected.
b) For each extra carbon copy — 3.00
a) Tracing cloth or drafting film material — P = 30.006.1.3 For lot data prepared on the prescribed LMB Form, the charge is
b) Tracing paper material — P = 18.00
a) For each page — P = 10.006.2 Survey Plan and Maps
6.2.1 | For the preparation or advance plan of lots of project surveys in tracing cloth to be certified by the LMB Director or his duly authorized representative, or the Regional Executive Director concerned, including all technical documents needed or registration proceedings, the charges shall be as follows: |
a) Per plan containing 1-10 corners — P = 330.00 | |
b) Per plan containing more than 10 corners — P = 335.00 |
6.2.2 | For the preparation and certification of a plan in tracing cloth, to be traced from an existing approved plan complete with bearing and distances of lot lines and tie lines, the fee shall be: |
Per plan containing 1-10 corners - P = 110.00 | |
Per plan containing more than 10 corners - P = 138.00 | |
6.2.3 | For the preparation of a plan in tracing cloth, to be copied from an existing approved plan, complete with bearings and distances of sides and tie-lines, but made on a reduced or enlarged scale, the fee shall be one hundred thirty two percent (132%) of the fee computed in paragraph 6.2.1. |
6.2.4 | When the preparation of the plan needs research, recomputation and/or reconstruction of the data from available survey records, the fee shall be one hundred fifty five percent (155%) of the fees prescribed in Paragraph 6.2.1. |
For all intent and purposes, the foregoing plans shall certified by the LMB Director or the concerned Regional Executive Director of their duly authorized representative/s provided that the source is an originally approved reconstructed plan. |
6.3.1 | For the preparation of special plans, location plans, sketch plans on tracing cloth of lots in cadastral public land subdivision, group settlement surveys, the data of which are available at the LMB Office, and when no field work is to be undertaken, the following rates per plan shall apply: |
For lots of 10 corners or less — P= 110.00 | |
For lots with more than 10 corners — P= 165.00 |
6.3.2 | For the preparation of sketch plans with bearings, distances and tie lines on tracing paper for reference purposes, directly traces from existing cadastral and public land subdivision maps: |
For lots of 1-10 corners — P=17.00 | |
For lots with more than 10 corners — P=22.00 | |
6.3.3 | For office investigation, preparation and certification of sketch plan on tracing cloth showing the relative positions of surveys, the survey plans of which are available in the Lands Management Bureau, the charges are: |
For plotting of 10 corners or less — P110.00 | |
For plotting of more than 10 corners — 165.00 | |
6.3.4 | For the foregoing cases, any common corner shall be counted as many times as there are lots to which it pertains. |
6.3.5 | The foregoing sketch plans shall be certified only by the Chief, Central Surveys Division or by the Chief, Regional Survey Division in which case sufficient documentary stamps shall be affixed to the document. |
6.4.1 | Preparation, verification and certification of copies of the Geodetic Engineers certificate and the Survey Notification Letter. |
For each certified copy of above document — P6.00 | |
6.4.2 | Certification in lieu of lost Geodetic Engineer's Certificate |
For the first page — P6.00 | |
For every additional copy — 1.00 | |
In all of the above cases, add one documentary stamp to be affixed to each document. | |
6.4.3 | Copying, verification and certification of field notes, lot data computations, traverse, solar computation sheets. |
Per sheet — P12.00 | |
6.4.4 | For document requiring research, recomputation and office verification: |
For the first page — P15.00 | |
For every succeeding page — 5.00 | |
7. | For furnishing plain reproduction copy of plans and maps (duly certified) |
7.1 | Diazo Paper/Print (White Print): per copy |
a) Isolated Plan (Prescribed LMB Form) P5.00 | |
b) One-minute Cadastral map 6.00 | |
c) Other map size for every square decimeter 0.35 |
8.1 | Certification of Position of Points of Reference: | ||
a) For research and certification of two (2) points or less — P20.00 | |||
b) For each reference point in excess of two (2) points — 2.50 | |||
8.2 | Verification and recomputation of lot lines, per line — 11.00 | ||
8.3 | For changing or amending the names of location appearing on the approved plan in order to conform to legal documents related to the land upon request of the survey claimant or his heirs, the fee per survey plan - 11.00 | ||
8.4 | For the cancellation of a previously approved survey plan upon the request of the survey claimant or his heirs or successor or assignee-in interest and favorably recommended by the Community Environment and Natural Resources Officer - P25.00 | ||
8.5 | For recomputation and verification of the area of lands covered by previously approved survey for purposes of amending the title: | ||
a) 1-10 corners or less - P22.00 | |||
b) For lot with more than 10 corners - 28.00 | |||
8.6 | For projection of mining surveys and certification or old surveys overlapped by the mining claim, the fees shall be: | ||
a) For each lot of 1-10 corners or less — P22.00 | |||
8.7 | For the tests of surveying materials and issuance of original authority to print L.M.B. Survey Forms including proof reading of the dummy: | ||
a) For each L.M.B. Form - P55.00 | |||
b) For renewal of the Authority using the same surveying materials as heretofore tested charge per L.M.B. Form shall be - P28.00 | |||
8.8 | For field test, examination, standardization, calibration and periodic field tests and recalibration, registration and certification of surveying instruments to be used in property surveys for land registration; general cleaning, repair and adjustments; and issuance of registration papers. | ||
8.8.1 | For field tests, examination, standardization, and original registration and certification of the surveying instruments: | ||
a) Electronic Distance Meter | —P150.00 | ||
b) Theodolite | — 100.00 | ||
c) Engineer's Transit | — 100.00 | ||
d) Engineer's Level | — 80.00 | ||
e) Surveying Steel Tape | — 60.00 | ||
f) Surveying Invar or Lovar type | — 60.00 | ||
g) Alidade | — 80.00 | ||
8.8.2 | For periodic re-examination, field test of calibration, an renewal of certificate of registration: | ||
a) | Electronic Distance Meter | — P100.00 | |
b) | Theodolite | — 75.00 | |
c) | Engineer's Transit | — 75.00 | |
d) | Engineer's Level | — 50.00 | |
e) | Surveying Steel Tape | — 45.00 | |
f) | Surveying Invar or Lovar type | — 45. 00 | |
g) | Alidade | — 50.00 | |
h) | Re-registration of the above instruments by change of ownership before the expiry date of the certificate | — 30.00 | |
i) | Issuance of certified true copy of the certificate of registration | ||
1. | For the first copy | 10.00 | |
2. | For each additional copy | 2.00 |
a) | Sale of photomosaic maps, original print, per copy — P10.00 |
Provided that for each additional copy of the same map sheet purchased, the cost shall be — 5.00 | |
b) | Philippine Plane Coordinate System at cost |
c) | Other Technical Bulletins as maybe published at cost |
a) For the use of the reactifier-enlarger, per hour — P35.008.9.4 Verification of Photogrammetric projects using the photogrammetric instrument At Cost
b) For the use of Photo-Laboratory facilities of processing tanks, washer, dryer, etc., per hour - 25.00
c) For the use of photo-contact printer, per hour - 25.00
d) For the use of the Universal stereo-planigraph instrument including space facilities, per hour - 60.00
The use of the machine shall be the subject a written contract with the Director of Lands.
1.1 | Application fee of FIFTY (P50.00) Pesos shall be charged per public Land Application as implemented by Lands Administrative Order No. 43. |
1.2 | Affidavit or Oath Fee of TEN (P10.00) Pesos shall be charged for each supporting document not on prescribed DENR Forms. |
2.1 | Transfer fee and fee for assignment in the nature of mortgage and fee for assignment of free patent right and other rights. |
2.1.1 | P10.00 per hectare for assignment of rights to agricultural lands covered by Free Patent Application but in no case less than P100.00 per application; and P100.00 for residential lands not exceeding 1,000 square meters. |
2.1.2 | P20.00 per hectare of lands applied for agricultural, educational, religious or charitable purposes, but in no case less than P150.00 nor more than P2,500 per application. |
2.1.3 | P200.00 for the first 1,000 square meters or fraction thereof of lands applied for residential, commercial, industrial or similar purposes plus P20.00 per 100 square meters or fraction therefor in excess of 1,000 square meters but in no case more than P2,000.00 per application. |
2.2 | Approval Fee for Service Contract under P.D. 151 and Joint Venture Agreement |
2.2.1 | P30.00 per hectare of lands applied for agricultural, educational, religious or charitable purposes, but in no case more than P300.00 per application of individual not more than P1,500 per application of corporation. |
2.2.2 | P200.00 per application for the first 1,000 square meters of fraction thereof of lands applied for residential, commercial, industrial or similar purposes, plus P10.00 per square meter or fraction thereof in excess of 1,000 square meters but in no case more than P2,000 per application. |
2.3 | Approval Fee for service contract under P.D. 151 and Joint Venture Agreement involving patented lands - P50.00 per hectare but in no case less than P500.00 nor more than P2,000.00 per application (request). |
2.4 | Approval Fee for the conveyance, alienation or encumbrance of patented lands - P10.00 per hectare but in no case less than P100.00 nor more than P500.00. |
2.5 | Service Fee for clearance required by banking and other financial institutions - P5.00 per hectare but in no case less than P100.00 nor more than P200.00. |
3. | Other Service Fees: |
3.1 | Reconstitution Fee |
3.1.1 | P150.00 per pre-war patent and deed of conveyance. |
3.1.2 | P100.00 per post-war patent and deed of conveyance. |
4. | Collection of fees incident to the filing and disposition of protest, appeals and other petitions in connection with the administrative settlement of claims and conflicts in public lands and or controversies on the private domain of the Republic of the Philippines as herein prescribed shall be: |
Pursuant to the provisions of Section 79 (B) of the Revised Administrative Code, Act No. 3038, and Section 5 of Commonwealth Act No. 141, otherwise known as "The Public Land Act", and in order to regulate the filing and disposition of claims or protests against public land applications, the resolutions of cases of conflicts between or among public land applications, and the prosecution of appeals or other petitions against decisions or orders of Regional Land Directors and the Director of Lands, the following fees shall be collected in the manner prescribed hereunder: | |
4.1 | Protest: For the filing of a protest required under paragraph number 4 of Lands Administrative Order No. 6, dated April 30, 1934, FIFTY (P50.00) Pesos shall be paid by the claimant before the claim is collected. |
This fee shall be collected and properly receipted for by the Director of Lands of his authorized representative. In case the fee is paid in any provincial unit, the receipt thereof or a certification of its payment should be attached to the protest when said protest is forwarded to the Central Office. | |
4.2 | Appeals: for filing an appeal from the decision or order of the Regional Land Director or the Director of Lands to the Minister of Natural Resources, under paragraph numbered 2 of Lands Administrative Order No. 6, SIXTY (P60.00) Pesos shall be paid by the appellant either to the Secretary of Environment and Natural Resources or to the Director of Lands or their respective duly authorized representative. Failure to pay the fee within the (10) days from the date of notice of appeal is filed may be sufficient ground for dismissal for dropping the appeal. |
4.3 | Orders of Execution: For the issuance of an order of execution, SIXTY (P60.00) Pesos to be paid the party requesting the execution. |
4.4 | Petition for Relief: For filing a petition for relief from the effect of a decision or order as provided in paragraph numbered 14 of Lands Administrative Order No. 6, SIXTY (P60.00) Pesos to be paid by the Petitioner. The same amount of fees shall be collected in connection with cases involving lands of the private domain of the government under the administration of the Director of Lands. |
4.5 | An amount equivalent to the actual traveling expenses but no less than P110.00 shall be deposited for the Bureau's witness services as requested by party in court cases where the Director of Lands is not a party in interest and in places beyond 50 km. radius from Manila. |
NOTE: Unless otherwise stated, all fees/charges prescribed under Title II hereof shall be paid by the applicant, transferee, assignee, vendee, mortgagee or the party requesting the approval/service. |
1.1.1 | P10.00 per certified copy of one page document. If document consists of more than one page the fee shall be P5.00 per additional pages. For certified xerox copy of Area Computation Book, the fee shall be P10.00 per sheet and P5.00 per additional sheet. |
1.1.2 | For certification regarding status of a lot or public land application the fee shall be P20.00. If more than one lot or more than one application the fee shall be P10.00 per additional lot or application. A fee of P20.00 per certification as to survey claimant of one (1) lot or isolated Plan. If more than one lot, P= 10.00 per additional lot. |
1.1.3 | P= 5.00 per page for plain photo copies only without certification. |
1.1.4 | P= 25.00 per certified xerox copy of approved Isolated Plans. |
1.1.5 | P= 20.00 per certified technical description in the LMB form No. V-37 per lot. |