(NAR) VOL. 22 NO. 3, JULY - SEPTEMBER 2011
- Variation Orders costing up to P2 Million shall be approved by the concerned District Engineer and Variation Orders costing above 2 Million but not exceeding P5 Million shall be approved by the concerned Regional Director.
It is hereby directed, however, that Variation Orders shall not involve additional funding requirement for the- project as contracted.- Certificate of Inspection prior to first and final payments for projects costing above P20 Million up to P50 Million shall be signed by the concerned Regional Director; and, for projects costing P20 Million and below, by the concerned District Engineer.