a) | set a standard bidding and awarding procedures in order to accelerate and facilitate the conduct of the cadastral survey of the entire country; and |
b) | formulate a mechanism to support the regional bidding and awarding committee (RBAC) in the bidding and awarding of cadastral projects |
a) | Cadastral Survey - a survey made of extensive areas covering an entire municipality or city consisting of several or many parcels of land undertaken for the purpose of land registration. |
b) | Bill of Quantities - a list of the specific items of the Work and their corresponding unit prices, lump sums, and/or provisional sums. It shall contain items of work for the construction, installation, testing, and commissioning of work to be done by the Contractor such as but not limited to establishment/recovery/conversion of main control points, manufacture and planting of monuments, reconnaissance and survey notification and other related survey activities. |
c) | Lot Survey - the field execution of defining the boundaries of the lots by using appropriate surveying instruments. |
d) | Political Boundary Survey - a survey showing the terrestrial extent or limit of a unit of government such as barangay, municipality and province. |
e) | Project Control Survey - a survey made for the purpose of establishing main and subsidiary control points for reference in the conduct of all kinds of survey. |
f) | Regular Cadastre - the conduct of cadastral survey which shall include the Project Control, Political Boundary and Lot Surveys. |
Chairman - | Chief, Surveys Division, Land Management Service |
Members - | 2 Geodetic Engineers from LMS |
1 Representative from Finance Division | |
1 Representative from Legal Division |
a) | Recommend to the RBAC the terms of reference and evaluation criteria for the bidding and awarding of cadastral survey in accordance with the approved standards and specification; and |
b) | Assist the RBAC in the eligibility screening and technical and financial evaluation and b) post qualification. |
a) | Category "A" Projects are composed of Regular Cadastre |
b) | Category "B" Projects are composed of Project Controls and Political Boundary surveys. |
c) | Category "C" Projects are the conduct of lot surveys and the related activities such as sketching, monumenting, and land use mapping on a modular basis. Modular Projects are the conduct of lot survey and the related activities covering a single barangay. |
i. Certification of good standing from the Geodetic Engineers of the Philippines Association;b. For Partnership or Corporation
ii. Sworn statement that he/she shall act as Project Chief for the project; and
iii. Geodetic Engineer's Profile/curriculum vitae
i. Current employment contract of the Project Chief who must be a registered Geodetic Engineer;SEC. 10. Qualifications of a Project Chief
ii. Certification of good standing of the Project Chief from the Geodetic Engineers of the Philippines Association;
iii. A board resolution certified by the Board Secretary for the Project Chief authorizing him/her to be the signatory of the contract; and
iv. Profile/curriculum vitae of all geodetic engineers involved in the Project
a. | Must be a licensed Geodetic Engineer as per R.A. 8560, as amended; |
b. | Had been a Chief of Party working from beginning to end on a cadastral or public land subdivision project or a complex subdivision project; |
c. | Has no pending or abandoned cadastral survey project previously contracted; |
d. | Shall not be involved in more than one (1) cadastral project during the contract implementation. |
e. | Has undergone an orientation workshop/seminar on cadastral projects conducted by the DENR in coordination with GEP or by the GEP in coordination with the DENR. |
PROJECT CHIEF | MEMBERS (GE) | |
Category "A" project | 1 | 2 |
Category "B" project | 1 | 1 |
Category "C" projects | 1 |
Category "A" | Category "B" | Category "C" | |
1) GPS Receivers | 3 | 3 | |
2) Total Stations | 3 | 2 | 2 |
3) One Second (1") | |||
Theodolite/Transit | 2 | ||
4) 100-m tapes (If no EDM or Total Station | 4 |